3153 1/2 W GARDEN AVE 90039
Certificate Information: 3153 1/2 W GARDEN AVE 90039
- Application / Permit
- 24014-20000-00393
- Plan Check / Job No.
- B24VN01190
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ADDITION.
- Permit Issued
- Issued on 4/10/2025
- Issuing Office
- Metro
- Current Status
- Issued on 4/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 2/3/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 2/8/2024 | APPLICANT |
| Applicant returned to address corrections | 11/7/2024 | HAYATO TSUCHIYA |
| Plan Check Approved | 11/12/2024 | ARAMIK SHAHMIRZAIAN |
| Issued | 4/10/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/17/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 10/17/2024 | WALLIE JONG |
| Construction near power lines | Cleared | 10/28/2024 | TINA MIRANDA |
| ZI | Cleared | 11/4/2024 | ASHLEY RODARTE |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2024 | WALLIE JONG |
| Sewer availability | Cleared | 11/6/2024 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/7/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 7/7/2025 | Partial Approval | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 9/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 9/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Rough | 9/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 10/2/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 10/2/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Rough | 10/2/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 10/2/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 10/2/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Rough | 10/2/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 10/30/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 10/30/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 10/30/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Drywall Nailing | 3/18/2026 | Approved | NICHOLAS LOPEZ |
| Shower Pan | 4/3/2026 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 4/24/2026 | Partial Approval | DAVID WILLIAMS |