6657 N NOBLE AVE 91405

Certificate Information: 6657 N NOBLE AVE 91405

Application / Permit
24014-20000-00383
Plan Check / Job No.
B24VN01170
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. New 207 sq. ft. addition at northerly side and at entry. Interior remodeling.
Permit Issued
Issued on 2/11/2024
Issuing Office
Current Status
CofO Issued on 11/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2024 APPLICANT
Assigned to Plan Check Engineer 1/31/2024 NGHI SU
Corrections Issued 1/31/2024 NGHI SU
Plan Check Approved 2/10/2024 AMY GUEVARRA
Issued 2/11/2024 APPLICANT
CofO in Progress 10/2/2024 RYAN SALAZAR
Permit Finaled 11/2/2024 DANIEL ORRANTE
CofO Issued 11/2/2024 DANIEL ORRANTE
Permit Finaled 11/2/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/7/2024 BRYAN GODINEZ
Roof/Waste drainage to street Cleared 2/7/2024 BRYAN GODINEZ
Sewer availability Cleared 2/7/2024 BRYAN GODINEZ
ZI Cleared 2/7/2024 JAZMIN ROQUE

Contact Information

Contractor Owner-Builder       ,
Engineer Mnatsakanyan,, Arthur; Lic. No.: C74802 4730 WOODMAN AVE STE 360      SHERMAN OAKS, CA 91423

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/21/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 3/26/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 5/3/2024 Approved RYAN SALAZAR
Green Building Rough 5/3/2024 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 5/3/2024 Approved RYAN SALAZAR
Underground Mechanical 5/3/2024 Approved RYAN SALAZAR
Insulation 5/21/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/21/2024 Partial Approval RYAN SALAZAR
Drywall Nailing 5/30/2024 Approved MATTHEW NELSON
Shower Pan 6/24/2024 Approved DAVID MATSON
Interior/Exterior Lathing 6/27/2024 Approved RYAN SALAZAR
Final 9/27/2024 Corrections Issued RYAN SALAZAR
Green Building Final 9/27/2024 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 9/27/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 9/27/2024 Approved RYAN SALAZAR
Final 10/1/2024 OK to Issue CofO RYAN SALAZAR
Green Building Final 10/1/2024 Approved RYAN SALAZAR
Service/Power Release 10/1/2024 Approved RYAN SALAZAR