10417 N MONTGOMERY AVE 91344

Certificate Information: 10417 N MONTGOMERY AVE 91344

Application / Permit
24014-20000-00376
Plan Check / Job No.
B24VN01159
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRREGULAR SHAPE ADDITION TO THE REAR OF THE (E) SINGLE FAMILY DWELLING. ALL WORK PER ENGINEER.
Permit Issued
Issued on 3/11/2024
Issuing Office
Current Status
CofO Issued on 10/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2024 APPLICANT
Assigned to Plan Check Engineer 2/7/2024 GIOVANNY CHAVEZ
Corrections Issued 2/8/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 2/21/2024 PINANK PATEL
Applicant returned to address corrections 2/24/2024 PINANK PATEL
Plan Check Approved 2/29/2024 PINANK PATEL
Issued 3/11/2024 APPLICANT
CofO in Progress 7/7/2025 CHRISTOPHER ROJAS
Permit Finaled 10/15/2025 RUBEN SALAS
CofO Issued 10/15/2025 RUBEN SALAS
Permit Finaled 10/15/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/10/2024 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 2/13/2024 JOHN LIN
Sewer availability Cleared 2/13/2024 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215       ,
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/27/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 4/1/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 4/25/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 4/25/2024 Partial Approval JAVIER RAMOS JR
Deputy Wood Construction 4/26/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 4/30/2024 Partial Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Partial Approval JOHN COLEMAN
Deputy Wood Construction 5/7/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 6/5/2024 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 6/5/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Approved JAVIER RAMOS JR
HVAC-Rough 6/5/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 6/5/2024 Approved JAVIER RAMOS JR
Green Building Rough 6/27/2024 Approved JAVIER RAMOS JR
Insulation 6/27/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/27/2024 Approved JAVIER RAMOS JR
Shower Pan 6/27/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 7/2/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 7/8/2024 Approved JAVIER RAMOS JR
Drywall Nailing 7/8/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 12/13/2024 Approved MICHEL ABAJAN
Final 12/13/2024 Corrections Issued MICHEL ABAJAN
Green Building Final 12/13/2024 Approved MICHEL ABAJAN
HVAC-Final 12/13/2024 Approved MICHEL ABAJAN
PLUMBING-Final 12/13/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/13/2024 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 12/13/2024 Approved MICHEL ABAJAN
Final 7/7/2025 OK to Issue CofO CHRISTOPHER ROJAS