REMOVE ALL THE EXTERIOR AND INTERIOR WALLS OF AN EXISTING DWELLING WITH ATTACHED TWO CAR GARAGE EXEMPT 5'3" LF AT THE SOUTH PORTION OF THE LOT AND BUILD AN 74'10" X 70'10" TWO STORY SINGLE FAMILY WITH ATTACHED TWO CAR GARAGE AND WITH ATTACHED ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33(C) AND (D), NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/1/2024
Issuing Office
Current Status
CofO Issued on 7/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/26/2024 APPLICANT
Assigned to Plan Check Engineer 2/1/2024 RARES BODEA
Corrections Issued 2/6/2024 RARES BODEA
Quality Review Completed 2/7/2024 STEVEN KIM
Building Plans Picked Up 2/9/2024 APPLICANT
Applicant returned to address corrections 6/26/2024 RARES BODEA
Plan Check Approved 7/30/2024 RARES BODEA
Issued 8/1/2024 APPLICANT
Permit Finaled 7/31/2025 KENNETH NAGLE
CofO Issued 7/31/2025 KENNETH NAGLE
Permit Finaled 7/31/2025 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 4/2/2024 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 4/5/2024 HISASHI KOBAYAKAWA
Sewer availability Cleared 4/5/2024 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 4/26/2024 MATTHEW CRAIG
GPI Written Notices Cleared 6/26/2024 RARES BODEA
Grading Pre-Inspection Cleared 6/26/2024 RARES BODEA
Specific Plan Cleared 7/18/2024 MOHAMMAD HASAN
Low Impact Development (LID) Cleared 7/24/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 7/25/2024 DARIN LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/14/2024 Not Ready for Inspection CARLOS MATAMOROS
Pre-Inspection 8/15/2024 Approved CARLOS MATAMOROS
Pre-Inspection 8/16/2024 Approved CARLOS MATAMOROS
Grading Pre-Inspection 10/18/2024 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 11/12/2024 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 11/14/2024 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 11/20/2024 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 11/22/2024 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 11/26/2024 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 12/10/2024 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 12/10/2024 Conditional Approval CARLOS MATAMOROS
Green Building Rough 12/10/2024 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 12/23/2024 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/23/2024 Partial Approval CHRISTOPHER WILSON
Green Building Rough 12/23/2024 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 1/17/2025 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 1/17/2025 Corrections Issued CARLOS MATAMOROS
Interior/Exterior Lathing 1/17/2025 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 1/23/2025 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 1/27/2025 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 1/27/2025 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 1/27/2025 Corrections Issued CARLOS MATAMOROS
Interior/Exterior Lathing 1/27/2025 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 1/27/2025 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 1/31/2025 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 1/31/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 2/3/2025 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 2/3/2025 Approved CARLOS MATAMOROS
HVAC-Rough 2/3/2025 Approved CARLOS MATAMOROS
Special/Order Compliance 2/3/2025 Corrections Issued MICHAEL PELHAM
BUILDING-Rough-Frame 2/5/2025 Corrections Issued CARLOS MATAMOROS
Green Building Rough 2/5/2025 Approved CARLOS MATAMOROS
Insulation 2/10/2025 Approved CARLOS MATAMOROS
Drywall Nailing 2/14/2025 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 7/1/2025 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Not Ready STEPHANIE SWANSON
Final 7/9/2025 Corrections Issued MEL KHACHATOURIAN
PLUMBING-Final 7/9/2025 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 7/11/2025 Approved STEPHANIE SWANSON
ELECTRICAL-Final 7/11/2025 Approved STEPHANIE SWANSON
Final 7/11/2025 Corrections Issued STEPHANIE SWANSON
Green Building Final 7/11/2025 Approved STEPHANIE SWANSON
HVAC-Final 7/11/2025 Approved STEPHANIE SWANSON
PLUMBING-Final 7/11/2025 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 7/11/2025 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 7/11/2025 Approved STEPHANIE SWANSON
Final 7/15/2025 Not Ready for Inspection JESUS PINEDA
Service/Power Release 7/17/2025 Approved MICHAEL PELHAM
Deputy Reinf. Concrete 7/30/2025 Conditional Approval MICHAEL PELHAM
Final 7/30/2025 Conditional Approval MICHAEL PELHAM