5455 N VANTAGE AVE 91607
Certificate Information: 5455 N VANTAGE AVE 91607
- Application / Permit
- 24014-20000-00358
- Plan Check / Job No.
- B24VN00729
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* 6' X 33' AND 3'-6" X 4" ADDITIONS TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 4/9/2024
- Issuing Office
- Current Status
- CofO Issued on 12/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | SELLA BENYAMIN |
| Corrections Issued | 1/30/2024 | SELLA BENYAMIN |
| Quality Review Completed | 2/7/2024 | STEVEN KIM |
| Plan Check Approved | 4/4/2024 | SELLA BENYAMIN |
| No Progress | 4/9/2024 | SELLA BENYAMIN |
| Plan Check Approved | 4/9/2024 | SELLA BENYAMIN |
| Plan Check Approved | 4/9/2024 | SELLA BENYAMIN |
| Issued | 4/9/2024 | APPLICANT |
| CofO in Progress | 12/4/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 12/14/2024 | RUBEN SALAS |
| Permit Finaled | 12/14/2024 | RUBEN SALAS |
| CofO Issued | 12/14/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 2/23/2024 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 2/27/2024 | CARLOS AGUILERA |
| Specific Plan | Cleared | 3/11/2024 | CHRISTIAN PEARSON |
| Sewer availability | Cleared | 4/1/2024 | LEE GUILBEAUX |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Owner-Builder | , |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 689 COUNTY SQUARE DR UNIT 32 VENTURA, CA 93003 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/15/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 4/17/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2024 | Corrections Issued | JOSE AVILA |
| Pre-Inspection | 4/26/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 5/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 5/6/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 5/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 5/14/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 5/16/2024 | Conditional Approval | JUAN VALENZUELA |
| Pre-Inspection | 5/17/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/10/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Wood Frame | 6/10/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 6/11/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/11/2024 | Approved | OGANES TARAKHCHYAN |
| Pre-Inspection | 6/13/2024 | No Access for Inspection | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 6/14/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 6/14/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 6/26/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/26/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 6/27/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/7/2024 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 8/7/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 8/26/2024 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 8/26/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 8/27/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/28/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 8/28/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 8/28/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/28/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/28/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 10/2/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 12/4/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 12/4/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |