1405 N GOLDEN GATE AVE 90026

Certificate Information: 1405 N GOLDEN GATE AVE 90026

Application / Permit
24014-20000-00343
Plan Check / Job No.
B24VN01048
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION OF SECOND STORY ACCESSORY DWELLING (32'-10" X 29' IRREGULAR SHAPE) ON TOP OF EXISTING GARAGE PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 12/24/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 VAHAN JIVALAGIAN
Corrections Issued 2/15/2024 VAHAN JIVALAGIAN
Quality Review Completed 2/21/2024 OMID HEDAYAT
Building Plans Picked Up 2/22/2024 APPLICANT
Applicant returned to address corrections 8/28/2024 VAHAN JIVALAGIAN
Applicant returned to address corrections 11/20/2024 VAHAN JIVALAGIAN
Plan Check Approved 11/22/2024 VAHAN JIVALAGIAN
Issued 12/24/2024 APPLICANT
CofO in Progress 4/23/2026 FREDDIE RIVERA
Permit Finaled 4/30/2026 DEROLD HAUFF
CofO Issued 4/30/2026 DEROLD HAUFF
Permit Finaled 4/30/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/19/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 3/21/2024 DAVID LOPEZ
Sewer availability Cleared 3/21/2024 DAVID LOPEZ
Low Impact Development (LID) Cleared 7/18/2024 ERNEST TSE
Grading Pre-Inspection Cleared 11/20/2024 VAHAN JIVALAGIAN
Roof/Waste drainage to street Cleared 11/21/2024 AMBER CAMPBELL

Contact Information

Contractor Marentes Construction; Lic. No.: 961891-B 38732 GLENBUSH AVE      PALMDALE, CA 93550
Engineer Galbreath,, Sean; Lic. No.: S5653 600 SOUTH LAKE AVE STE 308      PASADENA, CA 91106

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/2/2025 Partial Approval NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/14/2025 Corrections Issued ANTHONY RAMOS
BUILDING-Rough-Frame 1/17/2025 Partial Approval FREDDIE RIVERA
Special/Order Compliance 1/17/2025 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Partial Approval FREDDIE RIVERA
Insulation 1/22/2025 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 2/19/2025 Approved FREDDIE RIVERA
Shower Pan 3/5/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 3/12/2025 Approved REGINA MENDEZ
BUILDING-Rough-Frame 3/20/2025 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 3/20/2025 Approved FREDDIE RIVERA
Green Building Rough 3/20/2025 Partial Inspection FREDDIE RIVERA
HVAC-Rough 3/20/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 3/20/2025 Partial Inspection FREDDIE RIVERA
Deputy Wood Construction 3/21/2025 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/21/2025 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 3/25/2025 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 3/25/2025 Corrections Issued WILLIAM SIERRA
Green Building Rough 3/25/2025 Approved WILLIAM SIERRA
Interior/Exterior Lathing 4/1/2025 Approved OSVALDO PARAMO
Insulation 4/4/2025 Partial Approval ANTHONY RAMOS
Drywall Nailing 4/11/2025 Approved ANTHONY RAMOS
Insulation 4/11/2025 Approved ANTHONY RAMOS
Final 10/30/2025 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 10/30/2025 Approved FREDDIE RIVERA
Green Building Final 10/30/2025 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 10/30/2025 Approved FREDDIE RIVERA
Final 12/22/2025 Partial Inspection FREDDIE RIVERA
Green Building Final 12/22/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 12/22/2025 SGSOV Approved FREDDIE RIVERA
Final 4/20/2026 OK to Issue CofO FREDDIE RIVERA