6713-6715 N CASE AVE 91606
Certificate Information: 6713-6715 N CASE AVE 91606
- Application / Permit
- 24014-20000-00327
- Plan Check / Job No.
- B24VN00961
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan : CONVERT PORTION OF SFD TO ACCESSORY DWELLING UNIT (560 SQ-FT) WITH ADDITION PER LAMC 12.22 A.33(c) and (e) "COMPLY WITH DEPARTMENT ORDER effective date 06/12/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 2/28/2024
- Issuing Office
- Current Status
- CofO Issued on 1/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2024 | MOHAMMAD ESMAILI |
| Corrections Issued | 1/30/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 2/24/2024 | MOHAMMAD ESMAILI |
| Issued | 2/28/2024 | APPLICANT |
| CofO in Progress | 1/7/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 1/17/2025 | RUBEN SALAS |
| CofO Issued | 1/17/2025 | RUBEN SALAS |
| Permit Finaled | 1/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 1/31/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/4/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 4/15/2024 | Partial Approval | JENNIFER RABUCHIN |
| Pre-Inspection | 4/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 4/18/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 4/18/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 4/25/2024 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 4/25/2024 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 5/1/2024 | Partial Approval | JOHN HAYES |
| Deputy Drilled-In Anchors | 5/1/2024 | Conditional Approval | DAVID MATSON |
| Green Building Rough | 5/1/2024 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2024 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 5/21/2024 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 6/25/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 6/25/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 6/25/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/1/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 7/1/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 7/1/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 7/1/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/11/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 7/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 7/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 7/11/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/16/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 7/16/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 7/17/2024 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 7/23/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 7/23/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 7/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 8/1/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 8/16/2024 | Approved | MICHAEL CORTEZ |
| Final | 12/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 12/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 12/18/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 12/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 12/30/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 12/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 1/7/2025 | Approved | ROBERTO PALACIOS-LOPEZ |