6450 N WHITMAN AVE 91406

Certificate Information: 6450 N WHITMAN AVE 91406

Application / Permit
24014-20000-00294
Plan Check / Job No.
B24VN00863
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
***ePlan*** 1-story ADU addition to (E) det. garage per LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 3/4/2025
Issuing Office
Current Status
CofO Issued on 3/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 JOHNPAUL ISIP
Corrections Issued 1/29/2024 JOHNPAUL ISIP
Applicant returned to address corrections 5/21/2024 REZA HAGHIGHAT
Applicant returned to address corrections 6/14/2024 ALFREDO JARA
Applicant returned to address corrections 6/24/2024 REZA HAGHIGHAT
Plan Check Approved 7/24/2024 ALFREDO JARA
Issued 3/4/2025 APPLICANT
CofO in Progress 2/23/2026 GAREN HAYRAPETYAN
Permit Finaled 3/24/2026 RUBEN SALAS
CofO Issued 3/24/2026 RUBEN SALAS
Permit Finaled 3/24/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/30/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/31/2024 EDGAR ALCARAZ
Sewer availability Cleared 1/31/2024 EDGAR ALCARAZ
ZI Cleared 2/6/2024 BRENNEN OBETO
Low Impact Development (LID) Cleared 2/28/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 3/1/2024 EDGAR ALCARAZ
Construction near power lines Cleared 5/20/2024 RIDWAN HARDY

Contact Information

Contractor Adu Rc Builders; Lic. No.: 1080967-B       ,
Contractor Ca Construction Group Inc; Lic. No.: 1080967-B       ,
Engineer Nalbandian,, Serop Krekor; Lic. No.: M39801 1236 N COLUMBUS AVE UNIT 4      GLENDALE, CA 91202
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/17/2025 Partial Approval GAREN HAYRAPETYAN
Sewer 3/17/2025 Approved GAREN HAYRAPETYAN
Special/Order Compliance 3/17/2025 Corrections Issued GAREN HAYRAPETYAN
Underground Mechanical 3/17/2025 Approved GAREN HAYRAPETYAN
Deputy Drilled-In Anchors 3/21/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 3/24/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 3/24/2025 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 3/26/2025 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/22/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 6/3/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 6/3/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/10/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 6/10/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 6/10/2025 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 6/10/2025 Corrections Issued SALVADOR MARTINEZ
MERV13>=Rough 6/10/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/7/2025 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 7/7/2025 Approved MATTHEW NELSON
Green Building Rough 7/7/2025 Approved MATTHEW NELSON
HVAC-Rough 7/7/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/7/2025 Partial Approval MATTHEW NELSON
Insulation 7/24/2025 Corrections Issued SALVADOR MARTINEZ
Insulation 7/30/2025 Corrections Issued SALVADOR MARTINEZ
Insulation 8/26/2025 Approved WAYNE REGESTER
Drywall Nailing 9/4/2025 Approved GAREN HAYRAPETYAN
Shower Pan 9/4/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 12/18/2025 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 2/6/2026 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 2/6/2026 Approved GAREN HAYRAPETYAN
Final 2/6/2026 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 2/6/2026 Approved GAREN HAYRAPETYAN
Gas Test 2/6/2026 Approved GAREN HAYRAPETYAN
Green Building Final 2/6/2026 Approved GAREN HAYRAPETYAN
HVAC-Final 2/6/2026 Approved GAREN HAYRAPETYAN
MERV13>=Final 2/6/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Final 2/6/2026 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 2/6/2026 SGSOV Approved GAREN HAYRAPETYAN
Service/Power Release 2/6/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Smoke Detectors 2/6/2026 Approved GAREN HAYRAPETYAN
Final 2/23/2026 OK to Issue CofO GAREN HAYRAPETYAN
Service/Power Release 2/23/2026 Approved GAREN HAYRAPETYAN