6246 N CAMELLIA AVE 91606

Certificate Information: 6246 N CAMELLIA AVE 91606

Application / Permit
24014-20000-00293
Plan Check / Job No.
B24VN00858
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
13'-0" X 35'-0" ADDITION TO THE EXISTING SINGLE FAMILY DWELLING - ALL WORK PER WFPP
Permit Issued
Issued on 2/7/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2024 APPLICANT
Assigned to Plan Check Engineer 1/23/2024 DANIEL ABRAMYAN
Corrections Issued 1/23/2024 DANIEL ABRAMYAN
Plan Check Approved 1/31/2024 LUISANGEL VALENZUELA
Issued 2/7/2024 APPLICANT
CofO in Progress 9/5/2024 ROBERTO PALACIOS-LOPEZ
Permit Finaled 12/4/2024 RUBEN SALAS
CofO Issued 12/4/2024 RUBEN SALAS
Permit Finaled 12/4/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/26/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 1/29/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/3/2024 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 4/9/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/9/2024 Approved JOSE AVILA
Underground Mechanical 4/29/2024 Not Ready for Inspection JOHN HAYES
Wood Frame 4/29/2024 Corrections Issued JOHN HAYES
Underground Mechanical 5/3/2024 Partial Approval JOHN COLEMAN
Wood Frame 5/3/2024 Partial Approval JOHN COLEMAN
Insulation 5/9/2024 Corrections Issued LEONARD ROSS II
Insulation 5/13/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/21/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 6/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 6/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Wood Frame 6/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 7/3/2024 Approved JOSE AVILA
Insulation 7/3/2024 Approved JOSE AVILA
Interior/Exterior Lathing 7/3/2024 Approved JOSE AVILA
Drywall Nailing 7/10/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 7/10/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 8/29/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 8/29/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 8/29/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 8/29/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 9/5/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 9/5/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Green Building Final 9/5/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 9/5/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 9/5/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 9/5/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 9/5/2024 Approved ROBERTO PALACIOS-LOPEZ