17179 W TRIBUNE ST 91344

Certificate Information: 17179 W TRIBUNE ST 91344

Application / Permit
24014-20000-00287
Plan Check / Job No.
B24VN00842
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: 16' X 22' ADDITION TO AND CONVERT (E) DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT. WORK PER ENGINEERED DESIGN.
Permit Issued
Issued on 2/21/2024
Issuing Office
Current Status
CofO Issued on 8/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 OMAR GARNICA
Corrections Issued 1/26/2024 OMAR GARNICA
Plan Check Approved 2/5/2024 OMAR GARNICA
Issued 2/21/2024 APPLICANT
CofO in Progress 8/21/2024 DAVID SCANTLIN
Permit Finaled 8/21/2024 JOHN JANSON
CofO Issued 8/21/2024 JOHN JANSON
Permit Finaled 8/21/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/31/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 1/31/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 1/31/2024 CARLOS RAMIREZ
Sewer availability Cleared 1/31/2024 CARLOS RAMIREZ

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Ha My Design, Inc; Lic. No.: 999603-B       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/18/2024 Approved STEVEN BACK
PLUMBING-Rough 3/18/2024 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 4/4/2024 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Partial Approval STEVEN BACK
Green Building Rough 4/4/2024 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 4/17/2024 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 4/17/2024 Approved STEVEN BACK
Green Building Rough 4/17/2024 Approved STEVEN BACK
HVAC-Rough 4/17/2024 Approved STEVEN BACK
Interior/Exterior Lathing 4/17/2024 Partial Approval STEVEN BACK
PLUMBING-Rough 4/17/2024 Approved STEVEN BACK
Sewer 4/17/2024 Approved STEVEN BACK
BUILDING-Rough-Frame 5/2/2024 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/2/2024 Not Ready for Inspection STEVEN BACK
Insulation 5/2/2024 Corrections Issued STEVEN BACK
PLUMBING-Rough 5/2/2024 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Approved STEVEN BACK
Insulation 5/9/2024 Approved STEVEN BACK
Drywall Nailing 5/15/2024 Approved STEVEN BACK
Interior/Exterior Lathing 5/15/2024 Approved STEVEN BACK
Shower Pan 5/15/2024 Approved STEVEN BACK
Deputy Drilled-In Anchors 6/17/2024 Conditional Approval STEVEN BACK
Final 8/6/2024 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 8/6/2024 Approved STEVEN BACK
Green Building Final 8/6/2024 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 8/6/2024 SGSOV Approved STEVEN BACK
Smoke Detectors 8/6/2024 Approved STEVEN BACK
Final 8/20/2024 OK to Issue CofO DAVID SCANTLIN
Service/Power Release 8/21/2024 Approved DAVID SCANTLIN