6421 N DEMPSEY AVE 91406

Certificate Information: 6421 N DEMPSEY AVE 91406

Application / Permit
24014-20000-00285
Plan Check / Job No.
B24VN00833
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE WITH AN ADDITION TO A DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 6/21/2024
Issuing Office
Current Status
CofO Issued on 3/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 CARLOS MONTES
Corrections Issued 1/30/2024 CARLOS MONTES
Quality Review Completed 1/31/2024 PRANITA SHAH
Plan Check Approved 6/21/2024 CARLOS MONTES
Issued 6/21/2024 APPLICANT
CofO in Progress 3/11/2025 GAREN HAYRAPETYAN
Permit Finaled 3/18/2025 RUBEN SALAS
CofO Issued 3/18/2025 RUBEN SALAS
Permit Finaled 3/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/2/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 2/2/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 2/7/2024 CARLOS RAMIREZ
Sewer availability Cleared 2/7/2024 CARLOS RAMIREZ
ZI Cleared 3/20/2024 ASHLEY RODARTE
Construction near power lines Cleared 5/16/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Paniagua,, Cristobal; Lic. No.: NA72894       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/6/2024 Approved MISAEL ESPARZA
PLUMBING-Rough 9/23/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 9/26/2024 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 10/2/2024 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Corrections Issued SALVADOR MARTINEZ
Special/Order Compliance 10/23/2024 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 10/23/2024 Corrections Issued SALVADOR MARTINEZ
Deputy Wood Construction 10/25/2024 Conditional Approval RAUL OLAGI
Underground Mechanical 10/28/2024 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 11/18/2024 Partial Approval SALVADOR MARTINEZ
Green Building Rough 11/18/2024 Not Ready for Inspection SALVADOR MARTINEZ
MERV13>=Rough 11/18/2024 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 11/26/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 11/26/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 11/27/2024 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 11/27/2024 Approved SALVADOR MARTINEZ
PLUMBING-Rough 11/27/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 12/5/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 12/5/2024 Approved RYAN SALAZAR
Green Building Rough 12/5/2024 Approved RYAN SALAZAR
MERV13>=Rough 12/5/2024 Approved RYAN SALAZAR
Insulation 12/11/2024 Approved KEVIN BERBERYAN
Shower Pan 12/11/2024 Approved KEVIN BERBERYAN
Drywall Nailing 12/13/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 12/13/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 2/6/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Service/Power Release 2/6/2025 Corrections Issued GAREN HAYRAPETYAN
Special/Order Compliance 2/6/2025 Corrections Issued GAREN HAYRAPETYAN
ELECTRICAL-Final 2/19/2025 Corrections Issued GAREN HAYRAPETYAN
HVAC-Final 2/19/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Final 2/19/2025 Corrections Issued GAREN HAYRAPETYAN
Service/Power Release 2/19/2025 Corrections Issued GAREN HAYRAPETYAN
ELECTRICAL-Final 3/3/2025 Corrections Issued MISAEL ESPARZA
Final 3/3/2025 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 3/3/2025 Approved MISAEL ESPARZA
Green Building Final 3/3/2025 Approved MISAEL ESPARZA
MERV13>=Final 3/3/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 3/3/2025 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/3/2025 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 3/3/2025 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 3/3/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 3/6/2025 Corrections Issued RAUL OLAGI
MERV13>=Final 3/6/2025 Approved RAUL OLAGI
PLUMBING-Final 3/6/2025 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 3/6/2025 SGSOV Approved RAUL OLAGI
Final 3/10/2025 OK to Issue CofO GAREN HAYRAPETYAN
Smoke Detectors 3/10/2025 Approved GAREN HAYRAPETYAN