14705 W FOX ST 91345

Certificate Information: 14705 W FOX ST 91345

Application / Permit
24014-20000-00280
Plan Check / Job No.
B24VN00830
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* DEMO 143 SQ FT AND CONVERT EXISTING SINGLE FAMILY DWELLING TO NEW GARAGE; ADD 33'-2" X 77'-9" SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 8/23/2024
Issuing Office
Current Status
CofO Issued on 2/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 SELLA BENYAMIN
Corrections Issued 2/1/2024 SELLA BENYAMIN
Quality Review Completed 2/9/2024 STEVEN KIM
Applicant returned to address corrections 4/9/2024 SELLA BENYAMIN
Applicant returned to address corrections 7/23/2024 SELLA BENYAMIN
Plan Check Approved 8/17/2024 SELLA BENYAMIN
Issued 8/23/2024 APPLICANT
CofO in Progress 2/4/2026 MATTHEW NELSON
Permit Finaled 2/26/2026 RUBEN SALAS
CofO Issued 2/26/2026 RUBEN SALAS
Permit Finaled 2/26/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/13/2024 LEE GUILBEAUX
Sewer availability Cleared 2/13/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/13/2024 LEE GUILBEAUX
Hydrant and Access approval Cleared 3/23/2024 GILBERT URREA
Low Impact Development (LID) Cleared 8/8/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/8/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/5/2024 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 9/12/2024 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 9/23/2024 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 9/26/2024 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 10/2/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 10/4/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/7/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/7/2024 Partial Approval JENNIFER RABUCHIN
Green Building Rough 11/7/2024 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 11/7/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 11/15/2024 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/21/2024 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 11/21/2024 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 11/21/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 11/21/2024 Partial Approval JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 11/21/2024 Partial Approval JENNIFER RABUCHIN
Wood Frame 11/21/2024 Conditional Approval JENNIFER RABUCHIN
Pre-Inspection 11/25/2024 Not Ready for Inspection MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 11/25/2024 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 12/2/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 12/2/2024 Approved JENNIFER RABUCHIN
Insulation 12/2/2024 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 12/2/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/9/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 12/9/2024 Approved JENNIFER RABUCHIN
Green Building Rough 12/9/2024 Approved JENNIFER RABUCHIN
Insulation 12/9/2024 Approved JENNIFER RABUCHIN
Shower Pan 12/9/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/13/2024 Approved JENNIFER RABUCHIN
Gas Test 1/2/2025 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 1/2/2025 Approved JENNIFER RABUCHIN
Service/Power Release 1/29/2025 Corrections Issued JENNIFER RABUCHIN
Special/Order Compliance 1/29/2025 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 2/19/2025 Approved JENNIFER RABUCHIN
HVAC-Final 4/3/2025 Corrections Issued JENNIFER RABUCHIN
Final 7/17/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 7/17/2025 Approved JENNIFER RABUCHIN
MERV13>=Final 7/17/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/17/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/17/2025 Approved JENNIFER RABUCHIN
Final 2/2/2026 OK to Issue CofO MATTHEW NELSON