10350 W MCCORMICK ST 91601
Certificate Information: 10350 W MCCORMICK ST 91601
- Application / Permit
- 24014-20000-00276
- Plan Check / Job No.
- B24VN00814
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 29' x 21' AND 15'-9" x 6' ADDITION TO (E) SFD AND INTERIOR REMODEL OF (E) SFD. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 10/15/2024
- Issuing Office
- Current Status
- CofO Issued on 5/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 1/26/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 10/1/2024 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 10/4/2024 | ALEC MOUSAKHANIAN |
| Issued | 10/15/2024 | APPLICANT |
| CofO in Progress | 4/15/2026 | ROBERTO PALACIOS-LOPEZ |
| CofO in Progress | 5/7/2026 | RAUL OLAGI |
| Permit Finaled | 5/28/2026 | RUBEN SALAS |
| CofO Issued | 5/28/2026 | RUBEN SALAS |
| Permit Finaled | 5/28/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/8/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 9/26/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 9/26/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yeghiayan,, Armond; Lic. No.: C69935 | 16873 MCKEEVER ST GRANADA HILLS, CA 91344 |
| Engineer | Yeghiayan,, Armond; Lic. No.: NA69935 | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/22/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 12/2/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 12/11/2024 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2024 | Partial Approval | JOSE AVILA |
| Sewer | 12/27/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 2/18/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 4/10/2025 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 4/11/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 4/11/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 4/11/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 4/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/17/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 4/17/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 4/17/2025 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 4/17/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 4/17/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 4/25/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 4/25/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 4/25/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 4/25/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 4/25/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 4/29/2025 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/1/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 5/1/2025 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 5/1/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 6/26/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Final | 7/2/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/2/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/2/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/2/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 7/2/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 7/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 11/17/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 11/17/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 11/17/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 11/17/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 11/17/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 11/17/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 11/17/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 11/17/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 11/17/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 4/15/2026 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |