10910 N DES MOINES AVE 91326

Certificate Information: 10910 N DES MOINES AVE 91326

Application / Permit
24014-20000-00271
Plan Check / Job No.
B24VN00801
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 21'-1" x 8'-9" FRONT ADDITION AND 5'-9" x 29'-0" SIDE ADDITION TO THE (E) SINGLE FAMILY DWELLING. TO ENLARGE BEDROOM, STUDY, AND ADD NEW BATHROOM. ADDITION TO ENLARGE LIVING ROOM AND OPEN KITCHEN.
Permit Issued
Issued on 2/23/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2024 APPLICANT
Assigned to Plan Check Engineer 1/26/2024 JEROME MAGAT PALMA
Corrections Issued 1/27/2024 JEROME MAGAT PALMA
Building Plans Picked Up 1/30/2024 APPLICANT
Plan Check Approved 2/23/2024 GIOVANNY CHAVEZ
Issued 2/23/2024 APPLICANT
CofO in Progress 9/23/2024 DAVID SCANTLIN
Permit Finaled 9/24/2024 JOHN JANSON
CofO Issued 9/24/2024 JOHN JANSON
Permit Finaled 9/24/2024 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/31/2024 EDGAR ALCARAZ
Sewer availability Cleared 1/31/2024 EDGAR ALCARAZ
Grading Pre-Inspection Cleared 2/1/2024 CHARLES POWELL
Eng Process Fee Ord 176,300 Cleared 2/7/2024 EDGAR ALCARAZ
ZA Case Cleared 2/21/2024 NATHAN ROMINE

Contact Information

Contractor Nextdoor Construction And Remodeling Inc; Lic. No.: 1061320-B 18653 VENTURA BLVD #393      TARZANA, CA 91356
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/17/2024 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 6/17/2024 Approved DAVID SCANTLIN
Underground Mechanical 6/17/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 7/29/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 7/29/2024 Approved DAVID SCANTLIN
Green Building Rough 7/29/2024 Approved DAVID SCANTLIN
HVAC-Rough 7/29/2024 Approved DAVID SCANTLIN
PLUMBING-Rough 7/29/2024 Approved DAVID SCANTLIN
Insulation 8/1/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 8/1/2024 Partial Approval DAVID SCANTLIN
Shower Pan 8/1/2024 Approved DAVID SCANTLIN
Drywall Nailing 8/8/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 8/8/2024 Approved GEVORK IPCHYAN
Final 9/20/2024 OK to Issue CofO DAVID SCANTLIN
Footing/Foundation/Slab 9/20/2024 Approved DAVID SCANTLIN
Green Building Final 9/20/2024 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 9/20/2024 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 9/20/2024 Approved DAVID SCANTLIN