8323 S BARNSLEY AVE 90045

Certificate Information: 8323 S BARNSLEY AVE 90045

Application / Permit
24014-20000-00262
Plan Check / Job No.
B24VN00766
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 7/18/2024
Issuing Office
Valley
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2024 APPLICANT
Assigned to Plan Check Engineer 1/26/2024 JEROME MAGAT PALMA
Corrections Issued 1/27/2024 JEROME MAGAT PALMA
Building Plans Picked Up 1/30/2024 APPLICANT
Applicant returned to address corrections 2/15/2024 JESSE ARELLANO
Plan Check Approved 7/18/2024 ISIS ARGUETA
Issued 7/18/2024 APPLICANT
CofO in Progress 10/25/2024 TEMISTOCLES CAAL
Permit Finaled 10/25/2024 RICHARD STEINBACH
Permit Finaled 10/25/2024 RICHARD STEINBACH
CofO Issued 10/25/2024 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/7/2024 CHARLES POWELL
Address approval Cleared 2/20/2024 BRENDEN HAWK
Eng Process Fee Ord 176,300 Cleared 2/20/2024 BRENDEN HAWK
Sewer availability Cleared 2/20/2024 BRENDEN HAWK
Roof/Waste drainage to street Cleared 2/28/2024 VLADIMIR ARUTYUNYAN
Miscellaneous Cleared 3/6/2024 RUBEN VASQUEZ
Construction near power lines Cleared 6/21/2024 RIDWAN HARDY

Contact Information

Contractor Hamodot Isaac; Lic. No.: 1071940-B 2131 CENTURY PARK LANE 416      LOS ANGELES, CA 90067
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/24/2024 Partial Inspection BOBBY KEY
Footing/Foundation/Slab 7/29/2024 Approved BOBBY KEY
PLUMBING-Rough 7/31/2024 Partial Approval BOBBY KEY
Sewer 7/31/2024 Approved BOBBY KEY
ELECTRICAL-Rough 8/12/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/15/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 8/19/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Partial Approval BOBBY KEY
HVAC-Rough 8/19/2024 Conditional Approval BOBBY KEY
PLUMBING-Rough 8/19/2024 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 8/26/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Approved JESUS RODRIGUEZ
Green Building Rough 8/26/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 8/26/2024 Approved JESUS RODRIGUEZ
Insulation 8/26/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/26/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 8/26/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 8/30/2024 Approved JESUS RODRIGUEZ
Shower Pan 9/10/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 9/13/2024 Partial Approval BOBBY KEY
Shower Pan 9/13/2024 Approved BOBBY KEY
Interior/Exterior Lathing 9/16/2024 Approved BOBBY KEY
ELECTRICAL-Final 10/8/2024 Corrections Issued BOBBY KEY
Final 10/8/2024 Corrections Issued BOBBY KEY
HVAC-Final 10/8/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 10/8/2024 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Approved BOBBY KEY
ELECTRICAL-Final 10/21/2024 Approved BOBBY KEY
Final 10/21/2024 Not Ready for Inspection BOBBY KEY
HVAC-Final 10/21/2024 Approved BOBBY KEY
PLUMBING-Final 10/21/2024 Approved BOBBY KEY
Final 10/24/2024 OK to Issue CofO TEMISTOCLES CAAL
Green Building Final 10/24/2024 Approved TEMISTOCLES CAAL
Service/Power Release 10/24/2024 Approved TEMISTOCLES CAAL
Smoke Detectors 10/24/2024 Approved TEMISTOCLES CAAL