8112 N VANTAGE AVE 91605
Certificate Information: 8112 N VANTAGE AVE 91605
- Application / Permit
- 24014-20000-00247
- Plan Check / Job No.
- B24VN00730
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* TWO STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING; INTERIOR REMODEL
- Permit Issued
- Issued on 5/3/2024
- Issuing Office
- Current Status
- CofO Issued on 2/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | SELLA BENYAMIN |
| Corrections Issued | 1/30/2024 | SELLA BENYAMIN |
| Quality Review Completed | 2/7/2024 | STEVEN KIM |
| Plan Check Approved | 4/23/2024 | SELLA BENYAMIN |
| No Progress | 4/30/2024 | SELLA BENYAMIN |
| Plan Check Approved | 4/30/2024 | SELLA BENYAMIN |
| No Progress | 5/2/2024 | SELLA BENYAMIN |
| Plan Check Approved | 5/2/2024 | SELLA BENYAMIN |
| Issued | 5/3/2024 | APPLICANT |
| CofO in Progress | 5/14/2025 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 2/14/2026 | MICHAEL PELHAM |
| CofO Issued | 2/14/2026 | MICHAEL PELHAM |
| Permit Finaled | 2/14/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/10/2024 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 3/2/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Creative Construction Solutions; Lic. No.: 981370-B | 234 WEST LINDEN AVENUE UNIT A BURBANK, CA 91502 |
| Engineer | Posadas,, John Garcia; Lic. No.: NA30786 | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/31/2024 | Conditional Approval | ROBERT GOLD |
| Deputy Drilled-In Anchors | 6/4/2024 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 6/6/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/23/2024 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/23/2024 | Approved | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 10/23/2024 | Approved | MATTHEW NELSON |
| Insulation | 11/18/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/18/2024 | Partial Approval | MATTHEW NELSON |
| Drywall Nailing | 12/11/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/11/2024 | Approved | MATTHEW NELSON |
| Final | 5/9/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 5/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 5/9/2025 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 5/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 5/13/2025 | OK to Issue CofO | NICHOLAS TROWBRIDGE |