4408 N COLBATH AVE 91423
Certificate Information: 4408 N COLBATH AVE 91423
- Application / Permit
- 24014-20000-00226
- Plan Check / Job No.
- B24VN00679
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (22'-1"x25'-3"), 495 SQFT ADDITION OF A BEDROOM/BATH TO EXISTING 1-STORY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 11/22/2024
- Issuing Office
- Valley
- Current Status
- Issued on 11/22/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | PETER MOSESIAN |
| Corrections Issued | 1/27/2024 | PETER MOSESIAN |
| Quality Review Completed | 1/31/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 2/6/2024 | APPLICANT |
| Plan Check Approved | 11/13/2024 | PETER MOSESIAN |
| Issued | 11/22/2024 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 3/22/2024 | DALIA MOKAYED |
| Eng Process Fee Ord 176,300 | Cleared | 3/27/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 8/29/2024 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 9/9/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/25/2024 | BIAINA HARITUNIAN |
| Certificate of Compliance | Cleared | 10/8/2024 | MATHEW QUAN |
Contact Information
| Architect | Yotnegparian,, Alain Levon; Lic. No.: C26374 | 11541 DONA PEPITA PLACE STUDIO CITY, CA 91604 |
| Contractor | All Borders Construction Inc; Lic. No.: 917597-B | 19324 ROMAR STREET NORTHRIDGE, CA 91324 |
| Engineer | Koh,, William Kim; Lic. No.: S3473 | 5695 STARWOOD CT WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/14/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 1/15/2025 | Partial Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 1/27/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 1/30/2025 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 7/10/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 7/21/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 8/11/2025 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/11/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 8/11/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 8/11/2025 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 8/26/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 8/26/2025 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 8/29/2025 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 8/29/2025 | Approved | MISAEL ESPARZA |
| Insulation | 9/12/2025 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 9/24/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/24/2025 | Approved | MISAEL ESPARZA |
| Shower Pan | 9/24/2025 | Partial Inspection | MISAEL ESPARZA |
| Underground Mechanical | 11/26/2025 | Approved | MICHAEL CORTEZ |