10303 N LAUREL CANYON BLVD 91331

Certificate Information: 10303 N LAUREL CANYON BLVD 91331

Application / Permit
24014-20000-00186
Plan Check / Job No.
B24VN00551
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 12'-0' X 17'-9" (213 SF ) PORTION OF (E) ATTACHED PATIO COVER INTO A (N) BEDROOM, BATHROOM AND CLOSET FOR (E) SFD.
Permit Issued
Issued on 10/9/2024
Issuing Office
Valley
Current Status
Issued on 10/9/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/16/2024 APPLICANT
Assigned to Plan Check Engineer 1/16/2024 LUISANGEL VALENZUELA
Corrections Issued 1/16/2024 LUISANGEL VALENZUELA
Plan Check Approved 3/7/2024 ANGELICA MARTINEZ
Issued 10/9/2024 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 2/29/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/6/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/4/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 11/7/2024 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 11/7/2024 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 12/5/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 12/5/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 12/19/2024 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/19/2024 Partial Approval MICHEL ABAJAN
MERV13>=Rough 12/19/2024 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 12/19/2024 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 1/30/2025 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 1/30/2025 Corrections Issued MICHEL ABAJAN
MERV13>=Rough 1/30/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 1/30/2025 Corrections Issued MICHEL ABAJAN
BUILDING-Rough-Frame 2/13/2025 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 2/13/2025 Approved MICHEL ABAJAN
Insulation 2/21/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/21/2025 Approved MICHEL ABAJAN
Drywall Nailing 2/27/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 3/20/2025 Approved MICHEL ABAJAN
Final 3/20/2025 Corrections Issued MICHEL ABAJAN
HVAC-Final 3/20/2025 Approved MICHEL ABAJAN
MERV13>=Final 3/20/2025 Approved MICHEL ABAJAN
PLUMBING-Final 3/20/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/20/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 3/20/2025 Approved MICHEL ABAJAN