6844 N ENFIELD AVE 91335

Certificate Information: 6844 N ENFIELD AVE 91335

Application / Permit
24014-20000-00185
Plan Check / Job No.
B24VN00549
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE 15'-6" X 14'-6" PORTION OF THE (E) PATIO COVER TO EXTEND EXISTING BEDROOM, ADD NEW BATHROOM AND CLOSET. ALL WORK PER ENGINEER DESIGN.
Permit Issued
Issued on 1/26/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2024 APPLICANT
Assigned to Plan Check Engineer 1/16/2024 MADISON ODELL
Corrections Issued 1/16/2024 MADISON ODELL
Plan Check Approved 1/25/2024 LUISANGEL VALENZUELA
Issued 1/26/2024 APPLICANT
CofO in Progress 12/5/2025 ARUTYUN MADATYAN
Permit Finaled 12/18/2025 JOHN JANSON
Permit Finaled 12/18/2025 JOHN JANSON
CofO Issued 12/18/2025 JOHN JANSON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/22/2024 Conditional Approval JEFFREY BULL
Footing/Foundation/Slab 4/24/2024 Approved JEFFREY BULL
Insulation 5/1/2024 Partial Approval JEFFREY BULL
Special/Order Compliance 5/1/2024 Corrections Issued JEFFREY BULL
PLUMBING-Rough 5/31/2024 Approved JEFFREY BULL
ELECTRICAL-Rough 7/25/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 7/25/2024 Partial Approval JEFFREY BULL
Drywall Nailing 8/19/2024 Approved JEFFREY BULL
Green Building Rough 8/19/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 10/31/2025 Approved ARUTYUN MADATYAN
Final 10/31/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 10/31/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 10/31/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 12/5/2025 Approved ARUTYUN MADATYAN
Final 12/5/2025 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 12/5/2025 Approved ARUTYUN MADATYAN
HVAC-Final 12/5/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 12/5/2025 Approved ARUTYUN MADATYAN