5954 N CARPENTER AVE 91607

Certificate Information: 5954 N CARPENTER AVE 91607

Application / Permit
24014-20000-00178
Plan Check / Job No.
B24VN00530
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 24'-0" x 20'-0" ADDITION TO THE (E) SINGLE FAMILY DWELLING. NEW 16'-4" x 18'-0" ATTACHED CARPORT PER P/BC 2023-005.
Permit Issued
Issued on 2/18/2025
Issuing Office
Valley
Current Status
CofO Issued on 9/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2024 APPLICANT
Assigned to Plan Check Engineer 1/22/2024 JESSE ARELLANO
Corrections Issued 1/23/2024 JESSE ARELLANO
Building Plans Picked Up 4/11/2024 APPLICANT
Applicant returned to address corrections 11/8/2024 GIOVANNY CHAVEZ
Plan Check Approved 2/12/2025 NAREG ATARIAN
Issued 2/18/2025 APPLICANT
CofO in Progress 8/29/2025 ROBERTO PALACIOS-LOPEZ
CofO Issued 9/25/2025 RUBEN SALAS
Permit Finaled 9/25/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/18/2024 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 9/17/2024 DEBORA LEITE
Roof/Waste drainage to street Cleared 11/5/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/20/2025 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 2/25/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 2/25/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 2/27/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Pre-Inspection 3/11/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/25/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 3/25/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/25/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/25/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 3/25/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 3/25/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 4/3/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 4/3/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Drywall Nailing 4/16/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Rough 4/16/2025 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 5/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 5/20/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 7/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 7/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 7/10/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 7/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 7/10/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 7/10/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 8/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 8/21/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/25/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 8/25/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
Final 8/28/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ