7710 N FERNCOLA AVE 91352
Certificate Information: 7710 N FERNCOLA AVE 91352
- Application / Permit
- 24014-20000-00159
- Plan Check / Job No.
- B24VN00475
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 26'-11" x 21'-7" (IRREGULAR SHAPED) ADDITION TO (E) SFD. WORK DONE PER WFPP.
- Permit Issued
- Issued on 3/15/2024
- Issuing Office
- Current Status
- CofO Issued on 10/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2024 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 1/24/2024 | ARAMIK SHAHMIRZAIAN |
| Building Plans Picked Up | 2/1/2024 | APPLICANT |
| Issued | 3/15/2024 | APPLICANT |
| CofO in Progress | 10/1/2024 | DAVID ANDERSON |
| Permit Finaled | 10/22/2024 | DANIEL ORRANTE |
| CofO Issued | 10/22/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/22/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/9/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 3/15/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/12/2024 | Corrections Issued | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 4/24/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 4/26/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 5/1/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 5/8/2024 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 5/8/2024 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2024 | Partial Approval | DAVID ANDERSON |
| Insulation | 5/15/2024 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2024 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 6/12/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 6/21/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 6/21/2024 | Approved | DAVID ANDERSON |
| Insulation | 6/21/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 6/21/2024 | Partial Approval | DAVID ANDERSON |
| Drywall Nailing | 6/26/2024 | Approved | DAVID ANDERSON |
| Final | 9/6/2024 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/6/2024 | Approved | MATTHEW NELSON |
| Green Building Final | 9/6/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 9/6/2024 | Approved | MATTHEW NELSON |
| Final | 9/13/2024 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 9/13/2024 | SGSOV Approved | DAVID ANDERSON |
| Final | 9/30/2024 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 9/30/2024 | Approved | DAVID ANDERSON |