15747 W CHATSWORTH ST 91344

Certificate Information: 15747 W CHATSWORTH ST 91344

Application / Permit
24014-20000-00155
Plan Check / Job No.
B24VN00470
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan (N) 36'-0" X 22'-8" ADDITION TO (E) DETACHED GARAGE FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 4/17/2024
Issuing Office
Current Status
Issued on 4/17/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/18/2024 APPLICANT
Assigned to Plan Check Engineer 1/22/2024 ISIS ARGUETA
Corrections Issued 1/23/2024 ISIS ARGUETA
Plan Check Approved 4/16/2024 ISIS ARGUETA
Issued 4/17/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/8/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 2/14/2024 BRYAN GODINEZ
Sewer availability Cleared 2/14/2024 BRYAN GODINEZ
Low Impact Development (LID) Cleared 3/19/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 3/26/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/22/2024 Approved JENNIFER RABUCHIN
Special/Order Compliance 8/22/2025 Corrections Issued CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 9/23/2025 Corrections Issued CHRISTOPHER ROJAS
Underground Mechanical 9/23/2025 Partial Approval CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 9/30/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 9/30/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/23/2025 Partial Approval CHRISTOPHER ROJAS
Special/Order Compliance 10/23/2025 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 11/13/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 12/1/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Deputy Wood Construction 12/10/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/8/2026 Partial Approval CHRISTOPHER ROJAS
Special/Order Compliance 5/8/2026 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/22/2026 Approved GAREN HAYRAPETYAN
HVAC-Rough 5/22/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 5/22/2026 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 5/29/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 5/29/2026 Approved CHRISTOPHER ROJAS
MERV13>=Rough 5/29/2026 Approved CHRISTOPHER ROJAS
Insulation 6/9/2026 Approved CHRISTOPHER ROJAS
Drywall Nailing 6/25/2026 Approved CHRISTOPHER ROJAS
Shower Pan 6/25/2026 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 7/2/2026 Approved CHRISTOPHER ROJAS
Shower Pan 7/2/2026 Approved CHRISTOPHER ROJAS