8104-8108 N VANTAGE AVE 91605

Certificate Information: 8104-8108 N VANTAGE AVE 91605

Application / Permit
24014-20000-00144
Plan Check / Job No.
B24VN00446
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ADD NEW 35' X 24'-6" DWELLING PER SB 9 (8104 VANTAGE) TO EXISTING SINGLE FAMILY DWELLING (8106 VANTAGE); REMOVE 97 SQ FT OF GARAGE AND CONVERT TO NEW ACCESSORY DWELLING UNIT (8108 VANTAGE) PER LAMC 12.22 A.33(c) and (e); ADD 28'-6" X 26'-6" IRREGULAR SHAPE TO ENLARGE ADU AND ATTACH TO DUPLEX
Permit Issued
Issued on 4/2/2024
Issuing Office
Current Status
CofO Issued on 4/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2024 APPLICANT
Assigned to Plan Check Engineer 2/1/2024 SELLA BENYAMIN
Corrections Issued 2/9/2024 SELLA BENYAMIN
Quality Review Completed 2/15/2024 STEVEN KIM
Building Plans Picked Up 2/16/2024 APPLICANT
Plan Check Approved 4/2/2024 SELLA BENYAMIN
Issued 4/2/2024 APPLICANT
CofO in Progress 3/11/2026 MATTHEW NELSON
CofO Issued 4/16/2026 RUBEN SALAS
Permit Finaled 4/16/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/24/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 2/29/2024 EDGAR ALCARAZ
Sewer availability Cleared 2/29/2024 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 3/7/2024 TOMMY YIN
Senate Bill 9 Cleared 3/7/2024 ASHLEY RODARTE
Roof/Waste drainage to street Cleared 3/8/2024 EDGAR ALCARAZ
Miscellaneous Cleared 3/13/2024 SIMON LIU
Hydrant and Access approval Cleared 3/19/2024 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/23/2024 Corrections Issued MATTHEW NELSON
Underground Mechanical 9/11/2024 Corrections Issued MATTHEW NELSON
Special/Order Compliance 9/17/2024 Partial Inspection DAVID MATSON
Underground Mechanical 9/17/2024 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 10/18/2024 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Partial Approval MATTHEW NELSON
Underground Mechanical 1/28/2025 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 3/3/2025 Approved MATTHEW NELSON
PLUMBING-Rough 3/3/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 3/20/2025 Approved MATTHEW NELSON
Green Building Rough 3/20/2025 Approved MATTHEW NELSON
HVAC-Rough 3/20/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/16/2025 Partial Approval WILLIAM WREN
Insulation 5/6/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 5/14/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 6/5/2025 Approved MATTHEW NELSON
ELECTRICAL-Final 8/22/2025 Approved MATTHEW NELSON
Service/Power Release 8/27/2025 Approved MATTHEW NELSON
Final 3/4/2026 Corrections Issued MATTHEW NELSON
Green Building Final 3/4/2026 Approved MATTHEW NELSON
PLUMBING-Final 3/4/2026 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/4/2026 SGSOV Approved MATTHEW NELSON
Smoke Detectors 3/4/2026 Approved MATTHEW NELSON
Final 3/10/2026 OK to Issue CofO MATTHEW NELSON