10653-10657 N MATHER AVE 91040

Certificate Information: 10653-10657 N MATHER AVE 91040

Application / Permit
24014-20000-00112
Plan Check / Job No.
B24VN00320
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL & 22'-1" X 15'-11" ADDITION W/ PORCH TO (E) SFD, CONVERT ATTACHED GARAGE AND 22'-4" X 13'-5" PORTION OF SFD (564 SQFT) TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) AND 21'-5" X 15'-11" PORTION (327 SQFT) TO JR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22
Permit Issued
Issued on 7/10/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2024 APPLICANT
Assigned to Plan Check Engineer 1/17/2024 ARTIN ZARUKIAN
Corrections Issued 1/22/2024 ARTIN ZARUKIAN
Building Plans Picked Up 1/24/2024 APPLICANT
Applicant returned to address corrections 2/1/2024 KAMYAR EMAMI
Plan Check Approved 7/10/2024 ISIS ARGUETA
Issued 7/10/2024 APPLICANT
CofO in Progress 12/4/2025 NICHOLAS TROWBRIDGE
Permit Finaled 12/31/2025 RUBEN SALAS
CofO Issued 12/31/2025 RUBEN SALAS
Permit Finaled 12/31/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/16/2024 CARLOS AGUILERA
Grading Pre-Inspection Cleared 5/16/2024 GERMAN RODRIGUEZ MENDOZA
Roof/Waste drainage to street Cleared 5/16/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/20/2024 CARLOS AGUILERA
Watercourse Cleared 5/20/2024 CARLOS AGUILERA
Address approval Cleared 7/8/2024 CARLOS AGUILERA
Sewer availability Cleared 7/8/2024 CARLOS AGUILERA
Miscellaneous Cleared 7/9/2024 BRENNEN OBETO

Contact Information

Contractor Owner-Builder       ,
Engineer Mansuri,, Mehran; Lic. No.: C78614 14944 HESBY ST      SHERMAN OAKS, CA 91403

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/22/2024 Corrections Issued WILLIAM WREN
Excavation/Setback/Form/Re-Bar 9/12/2024 Approved WILLIAM WREN
Footing/Foundation/Slab 9/12/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 9/23/2024 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/21/2024 Corrections Issued WILLIAM WREN
ELECTRICAL-Rough 12/30/2024 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 12/30/2024 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 12/30/2024 Approved MATTHEW NELSON
Wood Frame 12/30/2024 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 1/15/2025 Approved WILLIAM WREN
HVAC-Rough 1/15/2025 Approved WILLIAM WREN
Insulation 1/30/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 1/30/2025 Partial Approval WILLIAM WREN
Drywall Nailing 2/6/2025 Partial Approval WILLIAM WREN
Drywall Nailing 2/12/2025 Approved WILLIAM WREN
Green Building Rough 2/12/2025 Approved WILLIAM WREN
Shower Pan 3/11/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 3/14/2025 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 8/21/2025 Not Ready for Inspection WILLIAM WREN
Final 8/21/2025 Not Ready for Inspection WILLIAM WREN
Green Building Final 8/21/2025 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 8/21/2025 SGSOV Approved WILLIAM WREN
Smoke Detectors 8/21/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 10/24/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 10/24/2025 Corrections Issued MISAEL ESPARZA
Final 10/24/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 10/24/2025 Approved MISAEL ESPARZA
HVAC-Final 10/24/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 10/24/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/10/2025 Approved KEVIN BERBERYAN
Final 11/10/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Final 12/3/2025 Approved NICHOLAS TROWBRIDGE
Final 12/3/2025 OK to Issue CofO NICHOLAS TROWBRIDGE
HVAC-Final 12/3/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Final 12/3/2025 Approved NICHOLAS TROWBRIDGE