1678 W 259TH ST 90710

Certificate Information: 1678 W 259TH ST 90710

Application / Permit
24014-20000-00107
Plan Check / Job No.
B24VN00311
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY (41'-5" X 34'-7" IRREGULAR SHAPE) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) - (d)
Permit Issued
Issued on 10/25/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2024 APPLICANT
Assigned to Plan Check Engineer 2/1/2024 VAHAN JIVALAGIAN
Corrections Issued 2/7/2024 VAHAN JIVALAGIAN
Quality Review Completed 2/9/2024 OMID HEDAYAT
Building Plans Picked Up 2/12/2024 APPLICANT
Applicant returned to address corrections 9/4/2024 VAHAN JIVALAGIAN
Applicant returned to address corrections 10/23/2024 VAHAN JIVALAGIAN
Plan Check Approved 10/25/2024 VAHAN JIVALAGIAN
Issued 10/25/2024 APPLICANT
CofO in Progress 8/29/2025 EUGENE CASSIDY
Permit Finaled 9/4/2025 ANSON MAGLASANG
CofO Issued 9/4/2025 ANSON MAGLASANG
Permit Finaled 9/4/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 2/21/2024 JILVER MAZARIEGOS
Eng Process Fee Ord 176,300 Cleared 4/8/2024 JILVER MAZARIEGOS
Sewer availability Cleared 4/8/2024 JILVER MAZARIEGOS
Construction near power lines Cleared 7/17/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 8/6/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/7/2024 JILVER MAZARIEGOS

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/24/2024 Corrections Issued EUGENE CASSIDY
METHANE-Barrier 12/24/2024 Approved EUGENE CASSIDY
METHANE-Subgrade 12/24/2024 Approved EUGENE CASSIDY
Footing/Foundation/Slab 1/7/2025 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/16/2025 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 2/11/2025 Approved EUGENE CASSIDY
HVAC-Rough 2/11/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 2/11/2025 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Approved EUGENE CASSIDY
Green Building Rough 2/27/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 2/27/2025 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 2/27/2025 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 3/14/2025 Partial Approval EUGENE CASSIDY
Green Building Rough 3/14/2025 Approved EUGENE CASSIDY
Insulation 3/14/2025 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 3/14/2025 Partial Approval EUGENE CASSIDY
Verify Sprinkler Sign Off 3/14/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 3/27/2025 Approved EUGENE CASSIDY
Drywall Nailing 3/27/2025 Approved EUGENE CASSIDY
Insulation 3/27/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 3/27/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 6/16/2025 Approved EUGENE CASSIDY
Final 6/16/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 6/16/2025 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 6/16/2025 Approved EUGENE CASSIDY
PLUMBING-Final 6/16/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Not Required EUGENE CASSIDY
Service/Power Release 6/16/2025 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 6/16/2025 Approved EUGENE CASSIDY
Final 7/11/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 7/11/2025 Approved EUGENE CASSIDY
Service/Power Release 7/11/2025 Approved EUGENE CASSIDY
Final 8/29/2025 OK to Issue CofO EUGENE CASSIDY