17404 W OSBORNE ST 91325

Certificate Information: 17404 W OSBORNE ST 91325

Application / Permit
24014-20000-00099
Plan Check / Job No.
B24VN00274
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: New addition, remodel and new attached patio cover to existing S.F.D.
Permit Issued
Issued on 4/15/2024
Issuing Office
Current Status
CofO Issued on 6/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2024 APPLICANT
Assigned to Plan Check Engineer 1/12/2024 CAROLEAN BASMA
Corrections Issued 1/16/2024 CAROLEAN BASMA
Plan Check Approved 4/12/2024 AMY GUEVARRA
Issued 4/15/2024 APPLICANT
CofO in Progress 4/21/2026 CHRISTOPHER ROJAS
Permit Finaled 6/4/2026 RUBEN SALAS
CofO Issued 6/4/2026 RUBEN SALAS
Permit Finaled 6/4/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/22/2024 COLIN LOREDO
Sewer availability Cleared 2/22/2024 COLIN LOREDO
Low Impact Development (LID) Cleared 4/3/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 4/4/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/3/2025 Corrections Issued NICHOLAS TROWBRIDGE
Deputy Drilled-In Anchors 4/15/2025 Conditional Approval RAUL OLAGI
Special/Order Compliance 4/16/2025 Corrections Issued NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 4/30/2025 Corrections Issued CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 4/30/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/30/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Wood Frame 5/5/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/6/2025 Corrections Issued CHRISTOPHER ROJAS
Insulation 5/6/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Sewer 5/6/2025 Partial Approval CHRISTOPHER ROJAS
Sewer 5/7/2025 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 5/9/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/9/2025 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 6/4/2025 Partial Approval DAVID ANDERSON
Deputy Wood Construction 6/5/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 6/30/2025 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/2/2025 Corrections Issued NICHOLAS TROWBRIDGE
HVAC-Rough 7/2/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 7/2/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 7/3/2025 Partial Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/10/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 7/10/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Rough 7/10/2025 Corrections Issued NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 7/11/2025 Approved NICHOLAS TROWBRIDGE
Gas Test 7/11/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 7/11/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 7/11/2025 Approved NICHOLAS TROWBRIDGE
Insulation 7/15/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 7/21/2025 Corrections Issued NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 7/21/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 7/22/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 7/24/2025 Approved MICHAEL CORTEZ
Wood Frame 7/29/2025 Approved NICHOLAS TROWBRIDGE
Shower Pan 8/11/2025 Not Ready for Inspection KATHRYN BUTTERWORTH
Shower Pan 8/12/2025 Approved KATHRYN BUTTERWORTH
Service/Power Release 8/22/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Service/Power Release 9/3/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 9/8/2025 No Access for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Final 9/22/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
HVAC-Final 9/22/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Final 9/22/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Smoke Detectors 9/22/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Final 10/1/2025 Approved NICHOLAS TROWBRIDGE
Final 10/3/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 10/3/2025 Approved NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 10/3/2025 SGSOV Approved NICHOLAS TROWBRIDGE
Smoke Detectors 10/3/2025 Approved NICHOLAS TROWBRIDGE
Final 4/16/2026 OK to Issue CofO CHRISTOPHER ROJAS