14907 W OTSEGO ST 91403
Certificate Information: 14907 W OTSEGO ST 91403
- Application / Permit
- 24014-20000-00094
- Plan Check / Job No.
- B24VN00258
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New two story 25' 10 1/2" x 26' 6" addition to existing SFD, NFPA 13D sprinkler is required. All work done per engineer.
- Permit Issued
- Issued on 4/10/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | NAREG ATARIAN |
| Corrections Issued | 1/27/2024 | NAREG ATARIAN |
| Quality Review Completed | 1/29/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 1/29/2024 | APPLICANT |
| Applicant returned to address corrections | 3/21/2024 | NAREG ATARIAN |
| Plan Check Approved | 4/10/2024 | NAREG ATARIAN |
| Issued | 4/10/2024 | APPLICANT |
| CofO in Progress | 4/21/2025 | JACK KARGODORIAN |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
| CofO Issued | 5/15/2025 | RUBEN SALAS |
| Permit Finaled | 5/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/22/2024 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2024 | COLIN LOREDO |
| Low Impact Development (LID) | Cleared | 3/18/2024 | MARCO SANCHEZ |
| "Q" conditions | Cleared | 3/19/2024 | YINGSHI HUANG |
| ZI | Cleared | 3/19/2024 | YINGSHI HUANG |
| Roof/Waste drainage to street | Cleared | 3/21/2024 | EDGAR ALCARAZ |
Contact Information
| Architect | Meschi,, Mamood; Lic. No.: C24312 | 5157 RUBIO AVENUE ENCINO, CA 91436 |
| Contractor | Arkieco - Construction Inc; Lic. No.: 761267-B | 5157 RUBIO AVENUE ENCINO, CA 91436 |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/29/2024 | Corrections Issued | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 5/1/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 5/6/2024 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2024 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 7/26/2024 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 7/26/2024 | Approved | JACK KARGODORIAN |
| Green Building Rough | 7/26/2024 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 7/26/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 7/26/2024 | Approved | JACK KARGODORIAN |
| Insulation | 8/7/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/7/2024 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 8/7/2024 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 8/14/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/14/2024 | Approved | JACK KARGODORIAN |
| Final | 4/2/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 4/2/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 4/2/2025 | SGSOV Gas Company | JACK KARGODORIAN |
| Smoke Detectors | 4/2/2025 | Approved | JACK KARGODORIAN |
| Final | 4/18/2025 | OK to Issue CofO | JACK KARGODORIAN |