14680-14682 W LIMEDALE ST 91402

Certificate Information: 14680-14682 W LIMEDALE ST 91402

Application / Permit
24014-20000-00090
Plan Check / Job No.
B24VN00243
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 33'-0" X 20'-0" ACCESSORY DWELLING UNIT TO THE EXISTING SINGLE FAMILY DWELLING PER LAMC 12.22 A.33(c) AND (e) - PER WFPP. TO REMOVE THE (E) PATIO COVER.
Permit Issued
Issued on 7/19/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2024 APPLICANT
Assigned to Plan Check Engineer 1/12/2024 DANIEL ABRAMYAN
Corrections Issued 1/12/2024 DANIEL ABRAMYAN
Building Plans Picked Up 1/17/2024 APPLICANT
Applicant returned to address corrections 5/7/2024 GIOVANNY CHAVEZ
Plan Check Approved 5/9/2024 LUISANGEL VALENZUELA
Issued 7/19/2024 APPLICANT
CofO in Progress 5/5/2026 JOSE AVILA
CofO Issued 5/14/2026 RUBEN SALAS
Permit Finaled 5/14/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/2/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/5/2024 CARLOS AGUILERA
Sewer availability Cleared 2/5/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 5/2/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 5/2/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/23/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 7/23/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 7/23/2024 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 7/25/2024 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/9/2024 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 8/12/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/12/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 8/26/2024 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 8/26/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/26/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 9/23/2024 Approved VINCENT HANLEY
Insulation 9/23/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 9/23/2024 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 9/23/2024 Approved VINCENT HANLEY
Drywall Nailing 9/27/2024 Approved JENNIFER RABUCHIN
Green Building Rough 9/27/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 9/27/2024 Partial Approval JENNIFER RABUCHIN
Sewer 2/7/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/30/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/30/2025 Corrections Issued JENNIFER RABUCHIN
Final 7/30/2025 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 7/30/2025 Approved JENNIFER RABUCHIN
Green Building Final 7/30/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/30/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 7/30/2025 Approved JENNIFER RABUCHIN
Final 10/31/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 10/31/2025 Approved NICHOLAS TROWBRIDGE
Final 4/13/2026 OK to Issue CofO JENNIFER RABUCHIN