14680-14682 W LIMEDALE ST 91402
Certificate Information: 14680-14682 W LIMEDALE ST 91402
- Application / Permit
- 24014-20000-00090
- Plan Check / Job No.
- B24VN00243
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 33'-0" X 20'-0" ACCESSORY DWELLING UNIT TO THE EXISTING SINGLE FAMILY DWELLING PER LAMC 12.22 A.33(c) AND (e) - PER WFPP. TO REMOVE THE (E) PATIO COVER.
- Permit Issued
- Issued on 7/19/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 1/12/2024 | DANIEL ABRAMYAN |
| Building Plans Picked Up | 1/17/2024 | APPLICANT |
| Applicant returned to address corrections | 5/7/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 5/9/2024 | LUISANGEL VALENZUELA |
| Issued | 7/19/2024 | APPLICANT |
| CofO in Progress | 5/5/2026 | JOSE AVILA |
| CofO Issued | 5/14/2026 | RUBEN SALAS |
| Permit Finaled | 5/14/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/5/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 5/2/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 5/2/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/23/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 7/23/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/23/2024 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 7/25/2024 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/12/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/12/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/26/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/26/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/26/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/23/2024 | Approved | VINCENT HANLEY |
| Insulation | 9/23/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 9/23/2024 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 9/23/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 9/27/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 9/27/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/27/2024 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 2/7/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/30/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/30/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 7/30/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/30/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 7/30/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/30/2025 | Approved | JENNIFER RABUCHIN |
| Final | 10/31/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 10/31/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 4/13/2026 | OK to Issue CofO | JENNIFER RABUCHIN |