18160-18164 W INGOMAR ST 91335

Certificate Information: 18160-18164 W INGOMAR ST 91335

Application / Permit
24014-20000-00052
Plan Check / Job No.
B24VN00173
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT (347 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22. PROPOSED IRR SHAPED 31'3"X25'10"ACCESSORY DWELLING UNIT ADDITION TO SFD AT REAR PER LAMC 12.22 A.33(c) and (e). IRREG SHAPED 16'6"X27'2" ADDITION TO EX DWELLING. MAJOR INT/EXT REMODEL. ALL CONSTRUCTION DESIGN PER ENGR. <NFPA-13D FIRE SPRINKLER SYSTEM THRU-OUT>
Permit Issued
Issued on 2/29/2024
Issuing Office
Valley
Current Status
CofO Issued on 2/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2024 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 JEROME MAGAT PALMA
Corrections Issued 1/11/2024 JEROME MAGAT PALMA
Building Plans Picked Up 1/18/2024 APPLICANT
Applicant returned to address corrections 2/16/2024 HAYATO TSUCHIYA
Plan Check Approved 2/29/2024 HAYATO TSUCHIYA
Issued 2/29/2024 APPLICANT
CofO in Progress 1/13/2025 ARUTYUN MADATYAN
Permit Finaled 2/7/2025 JOHN JANSON
CofO Issued 2/7/2025 JOHN JANSON
Permit Finaled 2/7/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/26/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/26/2024 LEE GUILBEAUX
Sewer availability Cleared 1/26/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/26/2024 LEE GUILBEAUX
Miscellaneous Cleared 1/29/2024 NELSON RODRIGUEZ
Low Impact Development (LID) Cleared 2/13/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 2/15/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/15/2024 Conditional Approval JEFFREY BULL
Footing/Foundation/Slab 3/18/2024 Approved JEFFREY BULL
Underground Mechanical 3/18/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Partial Approval DAVID SCANTLIN
Insulation 3/29/2024 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 3/29/2024 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Not Ready for Inspection JEFFREY BULL
Insulation 4/2/2024 Not Ready for Inspection JEFFREY BULL
Sewer 4/18/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 6/10/2024 Not Ready for Inspection JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Approved JEFFREY BULL
Green Building Rough 6/10/2024 Not Ready for Inspection JEFFREY BULL
Rough-Elec/Plmb/HVAC 6/10/2024 Partial Approval JEFFREY BULL
Wood Frame 6/10/2024 Not Ready for Inspection JEFFREY BULL
Interior/Exterior Lathing 6/18/2024 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 6/18/2024 Approved JEFFREY BULL
ELECTRICAL-Rough 6/21/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 6/21/2024 Partial Approval JEFFREY BULL
Shower Pan 6/25/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 7/1/2024 Approved MORRIS JACKSON
Insulation 7/5/2024 Approved JEFFREY BULL
Insulation 7/9/2024 Approved JEFFREY BULL
Drywall Nailing 7/17/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 11/22/2024 SGSOV No Gas ARUTYUN MADATYAN
BUILDING-Rough-Frame 12/11/2024 Approved ARUTYUN MADATYAN
Final 12/11/2024 Corrections Issued ARUTYUN MADATYAN
Green Building Final 12/11/2024 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Rough 12/11/2024 Approved ARUTYUN MADATYAN
Service/Power Release 12/11/2024 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 12/11/2024 Approved ARUTYUN MADATYAN
Final 1/9/2025 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Final 1/9/2025 Approved ARUTYUN MADATYAN
Service/Power Release 1/9/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Final 1/10/2025 Approved ARUTYUN MADATYAN
Final 1/10/2025 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 1/10/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 1/10/2025 Approved ARUTYUN MADATYAN
Service/Power Release 1/10/2025 Approved ARUTYUN MADATYAN