8261 N JUMILLA AVE 91306
Certificate Information: 8261 N JUMILLA AVE 91306
- Application / Permit
- 24014-20000-00051
- Plan Check / Job No.
- B24VN00169
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW ACCESSORY DWELLING UNIT ATTACHED TO (E) DETACHED GARAGE PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 7/25/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2024 | JESSE ARELLANO |
| Corrections Issued | 1/11/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 1/12/2024 | APPLICANT |
| Applicant returned to address corrections | 6/6/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 7/18/2024 | ISIS ARGUETA |
| Issued | 7/25/2024 | APPLICANT |
| CofO in Progress | 3/24/2025 | DAVID SCANTLIN |
| Permit Finaled | 9/6/2025 | MICHAEL PELHAM |
| CofO Issued | 9/6/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/6/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 1/18/2024 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2024 | COLIN LOREDO |
| Sewer availability | Cleared | 1/24/2024 | COLIN LOREDO |
| Low Impact Development (LID) | Cleared | 6/4/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 7/6/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | The New Beginning Construction Company; Lic. No.: 848904-B | 3837 E COCHRAN STREET SIMI VALLEY, CA 93063 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/24/2024 | Conditional Approval | HENRY KIM |
| PLUMBING-Rough | 10/4/2024 | Partial Approval | ALEXANDER HANDY |
| Sewer | 10/4/2024 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 10/4/2024 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 10/8/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 11/14/2024 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2024 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 11/14/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 11/14/2024 | Approved | ALEXANDER HANDY |
| Insulation | 11/25/2024 | Approved | SCOTT SOBEL |
| Interior/Exterior Lathing | 11/25/2024 | Partial Approval | SCOTT SOBEL |
| Insulation | 11/27/2024 | No Access for Inspection | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 11/27/2024 | No Access for Inspection | KRISTEN CAUSEY |
| Drywall Nailing | 12/9/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 12/9/2024 | Approved | GEVORK IPCHYAN |
| Shower Pan | 12/9/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 2/14/2025 | Approved | ALEXANDER HANDY |
| Final | 2/14/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 2/14/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Rough | 2/14/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 2/14/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 2/14/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 3/21/2025 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 3/21/2025 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 3/21/2025 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 3/21/2025 | Approved | DAVID SCANTLIN |
| Smoke Detectors | 3/21/2025 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 5/28/2025 | Corrections Issued | ALEXANDER HANDY |
| Special/Order Compliance | 8/26/2025 | Not Ready for Inspection | ALEXANDER HANDY |