11439 N SOPHIA AVE 91344

Certificate Information: 11439 N SOPHIA AVE 91344

Application / Permit
24014-20000-00010
Plan Check / Job No.
B24VN00029
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL THROUGHOUT INCLUDING KITCHEN,DINING ROOM,PANTRY AND MASTER BEDROOM W/NEW 363 SQFT GROUND FLOOR ADDITION TO EXISTING 1-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 1/30/2024
Issuing Office
Current Status
CofO Issued on 10/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2024 APPLICANT
Assigned to Plan Check Engineer 1/4/2024 PETER MOSESIAN
Corrections Issued 1/6/2024 PETER MOSESIAN
Quality Review Completed 1/9/2024 OMID HEDAYAT
Plan Check Approved 1/30/2024 PETER MOSESIAN
Issued 1/30/2024 APPLICANT
CofO in Progress 9/5/2024 JAVIER RAMOS JR
Permit Finaled 10/9/2024 DANIEL ORRANTE
CofO Issued 10/9/2024 DANIEL ORRANTE
Permit Finaled 10/9/2024 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/16/2024 CHARLES POWELL
Roof/Waste drainage to street Cleared 1/23/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/24/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/26/2024 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 2/26/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 2/26/2024 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 2/27/2024 Approved JOHN COLEMAN
PLUMBING-Rough 2/27/2024 Partial Approval JOHN COLEMAN
Sewer 2/27/2024 Partial Approval JOHN COLEMAN
Green Building Rough 3/8/2024 Not Ready for Inspection JAVIER RAMOS JR
Wood Frame 3/8/2024 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/13/2024 Partial Approval JAVIER RAMOS JR
Insulation 3/13/2024 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/3/2024 Corrections Issued MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 4/30/2024 Approved JAVIER RAMOS JR
HVAC-Rough 4/30/2024 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 4/30/2024 Not Ready for Inspection JAVIER RAMOS JR
Wood Frame 4/30/2024 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 5/2/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 5/2/2024 Not Ready for Inspection JAVIER RAMOS JR
Wood Frame 5/2/2024 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/7/2024 Approved JAVIER RAMOS JR
HVAC-Rough 5/7/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 5/7/2024 Approved JAVIER RAMOS JR
Insulation 5/14/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/14/2024 Partial Approval JAVIER RAMOS JR
Shower Pan 5/29/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 6/10/2024 Approved JAVIER RAMOS JR
Drywall Nailing 6/13/2024 Approved MICHEL ABAJAN
Green Building Rough 6/13/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 8/20/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 8/20/2024 Approved JAVIER RAMOS JR
Final 8/20/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 8/20/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 8/20/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 8/20/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/20/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 8/20/2024 Approved JAVIER RAMOS JR
Final 9/3/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 9/3/2024 Approved JAVIER RAMOS JR
Service/Power Release 9/24/2024 Approved JAVIER RAMOS JR