6332 N ORION AVE 91411

Certificate Information: 6332 N ORION AVE 91411

Application / Permit
24014-20000-00003
Plan Check / Job No.
B24VN00011
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
ADDITION TO AND CONVERT (E) DETACHED GARAGE TO (N) RECREATION ROOM, ATTACHED LAUNDRY ROOM, AND 3 ATTACHED COVERED PORCHES. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 2/13/2024
Issuing Office
Valley
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2024 APPLICANT
Assigned to Plan Check Engineer 1/8/2024 JESSE ARELLANO
Corrections Issued 1/9/2024 JESSE ARELLANO
Building Plans Picked Up 1/12/2024 APPLICANT
Plan Check Approved 1/25/2024 MADISON O'DELL
Issued 2/13/2024 APPLICANT
CofO in Progress 11/26/2024 RYAN SALAZAR
Permit Finaled 2/18/2025 RUBEN SALAS
CofO Issued 2/18/2025 RUBEN SALAS
Permit Finaled 2/18/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/19/2024 EDGAR ALCARAZ
Sewer availability Cleared 1/19/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/23/2024 EDGAR ALCARAZ

Contact Information

Contractor English Gary Construction Co; Lic. No.: 714893-B 326 S GRIFFITH PARK DR      BURBANK, CA 91506
Engineer Sayah,, Daniel H; Lic. No.: C67905 15233 VENTURA BLVD STE 1130      SHERMAN OAKS, CA 91403

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/27/2024 Partial Approval RYAN SALAZAR
Deputy Drilled-In Anchors 3/8/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 3/11/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 5/24/2024 Corrections Issued RYAN SALAZAR
BUILDING-Rough-Frame 6/11/2024 Partial Approval JAVIER RAMOS JR
Insulation 6/11/2024 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 6/11/2024 Partial Approval JAVIER RAMOS JR
Drywall Nailing 7/11/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 10/22/2024 Approved RYAN SALAZAR
Green Building Final 10/22/2024 Not Ready for Inspection RYAN SALAZAR
Green Building Rough 10/22/2024 Approved RYAN SALAZAR
Pre-Inspection 10/22/2024 Partial Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 10/22/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 10/22/2024 Approved RYAN SALAZAR
Final 11/20/2024 Corrections Issued RAUL OLAGI
Green Building Final 11/20/2024 Approved RAUL OLAGI
Final 11/25/2024 OK to Issue CofO RYAN SALAZAR