836 E 90TH ST 90002

Certificate Information: 836 E 90TH ST 90002

Application / Permit
24014-10002-05277
Plan Check / Job No.
B25LA02970
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL TO 24014-10000-05277 TO REVISE FLOOR PLAN AND SITE PLAN TO CAPTURE (N) ADDITIONAL AREA.
Permit Issued
Issued on 1/27/2025
Issuing Office
Current Status
Permit Finaled on 6/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2025 APPLICANT
Assigned to Plan Check Engineer 1/27/2025 EDWIN MARTINEZ
Plan Check Approved 1/27/2025 EDWIN MARTINEZ
Issued 1/27/2025 APPLICANT
Permit Finaled 6/9/2025 JOHN QUINTANILLA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/29/2025 Approved JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 1/31/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Conditional Approval JOHN QUINTANILLA
BUILDING-Rough-Frame 6/4/2025 No Access for Inspection JOHN QUINTANILLA
Final 6/4/2025 No Access for Inspection JOHN QUINTANILLA
Footing/Foundation/Slab 6/4/2025 No Access for Inspection JOHN QUINTANILLA
Green Building Final 6/4/2025 No Access for Inspection JOHN QUINTANILLA
Green Building Rough 6/4/2025 No Access for Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 6/9/2025 Approved JOHN QUINTANILLA
Final 6/9/2025 Permit Finaled JOHN QUINTANILLA
Footing/Foundation/Slab 6/9/2025 Approved JOHN QUINTANILLA
Green Building Final 6/9/2025 Approved JOHN QUINTANILLA
Green Building Rough 6/9/2025 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 6/11/2025 Approved LUIS CASTRO
Green Building Final 6/11/2025 Approved LUIS CASTRO
Green Building Rough 6/11/2025 Approved LUIS CASTRO