820 N LEONARD ROAD 90049

Certificate Information: 820 N LEONARD ROAD 90049

Application / Permit
24014-10001-03640
Plan Check / Job No.
B24WL09942
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental to permit# 24014-30000-03640 to add new attached recreation room
Permit Issued
Issued on 2/10/2025
Issuing Office
Current Status
CofO in Progress on 5/27/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/19/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 HOOMAN HAJIZADEH
Corrections Issued 12/24/2024 HOOMAN HAJIZADEH
Plan Check Approved 2/7/2025 HOOMAN HAJIZADEH
Issued 2/10/2025 APPLICANT
CofO in Progress 5/27/2026 KEVIN SARGSYAN

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/24/2024 HOOMAN HAJIZADEH
Eng Process Fee Ord 176,300 Cleared 1/13/2025 HISASHI KOBAYAKAWA
Sewer availability Cleared 1/13/2025 HISASHI KOBAYAKAWA
Watercourse Cleared 1/13/2025 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 1/15/2025 JERRY KAO
Roof/Waste drainage to street Cleared 1/16/2025 HISASHI KOBAYAKAWA

Contact Information

Contractor Landmark Building & Design Inc; Lic. No.: 982610-B       ,
Contractor Level 42 Construction; Lic. No.: 982610-B       ,
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 347 ROBERTSON BLVD      BEVERLY HILLS, CA 90211
Engineer Yu,, Irene; Lic. No.: C68382 3411 CAROLINE AVE      CULVER CITY, CA 90232
Engineer Yu,, Irene; Lic. No.: NA68382       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/20/2025 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/5/2025 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 4/1/2025 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 4/1/2025 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 4/1/2025 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 4/11/2025 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 4/11/2025 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 4/11/2025 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/18/2025 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 6/13/2025 Corrections Issued KEVIN SARGSYAN
FLOOD-Proofing Certificate 6/13/2025 Approved KEVIN SARGSYAN
Green Building Rough 6/13/2025 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 6/13/2025 Approved KEVIN SARGSYAN
Verify Sprinkler Sign Off 6/13/2025 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 6/30/2025 Approved KEVIN SARGSYAN
Green Building Rough 6/30/2025 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 6/30/2025 Approved KEVIN SARGSYAN
PLUMBING-Rough 6/30/2025 Approved KEVIN SARGSYAN
Shower Pan 6/30/2025 Approved KEVIN SARGSYAN
Insulation 7/9/2025 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 7/9/2025 Approved KEVIN SARGSYAN
Drywall Nailing 7/21/2025 No Access for Inspection KEVIN SARGSYAN
Drywall Nailing 7/23/2025 Approved KEVIN SARGSYAN
Final 5/27/2026 OK to Issue CofO KEVIN SARGSYAN
Green Building Final 5/27/2026 Approved KEVIN SARGSYAN
Smoke Detectors 5/27/2026 Approved KEVIN SARGSYAN