1567 W 228TH ST 90501
Certificate Information: 1567 W 228TH ST 90501
- Application / Permit
- 24014-10001-03160
- Plan Check / Job No.
- B25LA05788
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Supplemental to 24014-10000-03160 to change scope of work to New ADU per ordinance LAMC 12.22 A.33(c) and (d) and update inventory to reflect new building.
- Permit Issued
- Issued on 4/8/2025
- Issuing Office
- Current Status
- Permit Finaled on 4/30/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2025 | MINA HABILI |
| Corrections Issued | 2/22/2025 | MINA HABILI |
| Applicant returned to address corrections | 3/28/2025 | RICARDO RAMIREZ |
| Plan Check Approved | 4/1/2025 | RICARDO RAMIREZ |
| Issued | 4/8/2025 | APPLICANT |
| Permit Finaled | 4/30/2026 | EUGENE CASSIDY |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/1/2025 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2025 | BRYAN GODINEZ |
Contact Information
| Architect | Baek,, Sunpil; Lic. No.: NA35323 | , |
| Contractor | Jnk Builder Inc; Lic. No.: 1002330-B | , |
| Engineer | Hwang,, Junho; Lic. No.: NA5592 | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/2/2025 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Barrier | 5/2/2025 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 5/2/2025 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/8/2025 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/13/2025 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/23/2025 | Partial Approval | EUGENE CASSIDY |
| METHANE-Rough | 5/23/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/23/2025 | Partial Approval | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 5/23/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Partial Approval | EUGENE CASSIDY |
| Insulation | 6/4/2025 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/11/2025 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Rough | 9/11/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Interior/Exterior Lathing | 9/11/2025 | Conditional Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 9/11/2025 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/1/2025 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/1/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/1/2025 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 10/1/2025 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/17/2025 | Corrections Issued | EUGENE CASSIDY |
| Drywall Nailing | 1/9/2026 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Rough | 1/9/2026 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/10/2026 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 3/10/2026 | Approved | EUGENE CASSIDY |
| Insulation | 3/10/2026 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 3/10/2026 | Approved | EUGENE CASSIDY |
| Final | 3/24/2026 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 3/24/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 3/24/2026 | Approved | EUGENE CASSIDY |
| Final | 3/27/2026 | Corrections Issued | BEN MOLSTAD |
| Service/Power Release | 3/27/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 4/20/2026 | Corrections Issued | BEN MOLSTAD |
| Service/Power Release | 4/20/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 4/28/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 4/28/2026 | Not Required | EUGENE CASSIDY |
| Final | 4/30/2026 | Permit Finaled | EUGENE CASSIDY |