7737 N BELLAIRE AVE 91605
Certificate Information: 7737 N BELLAIRE AVE 91605
- Application / Permit
- 24014-10000-05757
- Plan Check / Job No.
- B24LA38141
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to (E) single family dwelling with attached garage.
- Permit Issued
- Issued on 1/24/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2024 | ALEXANDER JOO |
| Corrections Issued | 12/31/2024 | ALEXANDER JOO |
| Plan Check Approved | 1/22/2025 | CRISTINA SALAZAR |
| Issued | 1/24/2025 | APPLICANT |
| CofO in Progress | 9/11/2025 | VINCENT HANLEY |
| CofO Issued | 9/18/2025 | RUBEN SALAS |
| Permit Finaled | 9/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/15/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/15/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/6/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/13/2025 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 5/13/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 5/13/2025 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 5/13/2025 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/21/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/21/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 5/21/2025 | Approved | VINCENT HANLEY |
| Insulation | 5/27/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 5/27/2025 | Approved | MICHAEL CORTEZ |
| Insulation | 6/23/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/23/2025 | Approved | VINCENT HANLEY |
| Drywall Nailing | 6/30/2025 | Approved | VINCENT HANLEY |
| Shower Pan | 7/7/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 7/10/2025 | Approved | VINCENT HANLEY |
| Final | 8/29/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 8/29/2025 | Approved | VINCENT HANLEY |
| MERV13>=Final | 8/29/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 8/29/2025 | Approved | VINCENT HANLEY |
| Final | 9/11/2025 | OK to Issue CofO | VINCENT HANLEY |