507 N HIGHLAND AVE 90036

Certificate Information: 507 N HIGHLAND AVE 90036

Application / Permit
24014-10000-05755
Plan Check / Job No.
B24LA38133
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1. FIRST FLOOR INTERIOR REMODEL (AREA RENOVATION= 435 SQ. FT.). 2. (E) ATTACHED COVERED PATIO AREA TO BE CONVERTED INTO LIVING SPACE, 116 S.F.
Permit Issued
Issued on 5/16/2025
Issuing Office
Current Status
CofO Issued on 5/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2025 APPLICANT
Assigned to Plan Check Engineer 1/6/2025 LUKE GONZALES
Corrections Issued 1/7/2025 LUKE GONZALES
Plan Check Approved 4/21/2025 ZAW HAN
Issued 5/16/2025 APPLICANT
CofO in Progress 5/14/2026 CRAIG VAUGHAN
Permit Finaled 5/16/2026 DEROLD HAUFF
CofO Issued 5/16/2026 DEROLD HAUFF
Permit Finaled 5/16/2026 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 1/9/2025 JASON CHAN
HPOZ Cleared 4/18/2025 SUKI GERSHENHORN

Contact Information

Contractor Hani Custom Homes Inc; Lic. No.: 1123409-B       ,
Contractor Hani Custom Homes Llc; Lic. No.: 1123409-B       ,
Engineer Kashe,, Andrew; Lic. No.: C94117 984 SILVERTIP DR      DIAMOND BAR, CA 91765
Engineer Kashe,, Andrew; Lic. No.: NA94117       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/9/2025 Conditional Approval ROY SPAULDING
ELECTRICAL-Rough 7/15/2025 Approved CRAIG VAUGHAN
HVAC-Rough 7/15/2025 Approved CRAIG VAUGHAN
PLUMBING-Rough 7/15/2025 Approved CRAIG VAUGHAN
Wood Frame 7/15/2025 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 7/16/2025 Approved CRAIG VAUGHAN
Insulation 7/16/2025 Approved CRAIG VAUGHAN
Drywall Nailing 7/18/2025 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 8/29/2025 Approved CRAIG VAUGHAN
ELECTRICAL-Final 8/29/2025 Approved CRAIG VAUGHAN
Final 8/29/2025 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 8/29/2025 Approved CRAIG VAUGHAN
Green Building Final 8/29/2025 Approved CRAIG VAUGHAN
Green Building Rough 8/29/2025 Approved CRAIG VAUGHAN
HVAC-Final 8/29/2025 Approved CRAIG VAUGHAN
METHANE-Barrier 8/29/2025 Approved CRAIG VAUGHAN
METHANE-Final 8/29/2025 Approved CRAIG VAUGHAN
METHANE-Rough 8/29/2025 Approved CRAIG VAUGHAN
METHANE-Subgrade 8/29/2025 Approved CRAIG VAUGHAN
PLUMBING-Final 8/29/2025 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/29/2025 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 8/29/2025 Approved CRAIG VAUGHAN
Final 5/13/2026 OK to Issue CofO CRAIG VAUGHAN