2687 W CUNARD ST 90065

Certificate Information: 2687 W CUNARD ST 90065

Application / Permit
24014-10000-05714
Plan Check / Job No.
B24LA37863
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT (E) DETACHED GARAGE/CARPORT TO AN ACCESSORY DWELLING UNIT PER GCS 66323(a)(1)
Permit Issued
Issued on 5/15/2025
Issuing Office
Current Status
CofO Issued on 11/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2024 APPLICANT
Assigned to Plan Check Engineer 1/16/2025 VIVIAN LAO
Corrections Issued 1/22/2025 VIVIAN LAO
Quality Review Completed 1/24/2025 GARO TELMI
Applicant returned to address corrections 3/19/2025 VIVIAN LAO
Applicant returned to address corrections 4/11/2025 VIVIAN LAO
Plan Check Approved 5/13/2025 VIVIAN LAO
Issued 5/15/2025 APPLICANT
CofO in Progress 11/14/2025 RONNIE MEDINA
Permit Finaled 11/15/2025 DEROLD HAUFF
CofO Issued 11/15/2025 DEROLD HAUFF
Permit Finaled 11/15/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/6/2025 LANNY MERRICK
Address approval Cleared 3/8/2025 ERIK BEASLEY
Roof/Waste drainage to street Cleared 3/8/2025 ERIK BEASLEY
Sewer availability Cleared 3/8/2025 ERIK BEASLEY
Hydrant and Access approval Cleared 3/12/2025 JERRY KAO
Eng Process Fee Ord 176,300 Cleared 3/13/2025 ERIK BEASLEY

Contact Information

Contractor Cal - For Construction Inc; Lic. No.: 1021371-B       ,
Engineer Ilasin,, John Lacebal; Lic. No.: NA67469       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/3/2025 Partial Approval REGINA MENDEZ
Footing/Foundation/Slab 6/11/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 6/26/2025 Not Ready for Inspection DAVID WILLIAMS
Green Building Rough 6/26/2025 Not Ready for Inspection DAVID WILLIAMS
MERV13>=Rough 6/26/2025 Approved DAVID WILLIAMS
Interior/Exterior Lathing 7/30/2025 Approved REGINA MENDEZ
BUILDING-Rough-Frame 8/6/2025 Approved DAVID WILLIAMS
ELECTRICAL-Rough 8/6/2025 Approved DAVID WILLIAMS
Green Building Rough 8/6/2025 Approved DAVID WILLIAMS
HVAC-Rough 8/6/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 8/6/2025 Approved DAVID WILLIAMS
Insulation 8/12/2025 Approved REGINA MENDEZ
Drywall Nailing 8/19/2025 Partial Approval GEM DE OCAMPO
Shower Pan 8/21/2025 Approved GEM DE OCAMPO
Interior/Exterior Lathing 8/25/2025 Approved GEM DE OCAMPO
Drywall Nailing 11/5/2025 Approved RONNIE MEDINA
ELECTRICAL-Final 11/5/2025 Corrections Issued RONNIE MEDINA
Final 11/5/2025 Not Ready for Inspection RONNIE MEDINA
Green Building Final 11/5/2025 Approved RONNIE MEDINA
HVAC-Final 11/5/2025 Approved RONNIE MEDINA
MERV13>=Final 11/5/2025 Approved RONNIE MEDINA
PLUMBING-Final 11/5/2025 Corrections Issued RONNIE MEDINA
SGSOV-Seismic Gas S/O Valve 11/5/2025 SGSOV Approved RONNIE MEDINA
Smoke Detectors 11/5/2025 Approved RONNIE MEDINA
ELECTRICAL-Final 11/13/2025 Approved RONNIE MEDINA
Final 11/13/2025 OK to Issue CofO RONNIE MEDINA
HVAC-Final 11/13/2025 Approved RONNIE MEDINA
PLUMBING-Final 11/13/2025 Approved RONNIE MEDINA