3499 N OAK GLEN DR 90068

Certificate Information: 3499 N OAK GLEN DR 90068

Application / Permit
24014-10000-05707
Plan Check / Job No.
B24LA37829
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ADDITION AND CONVERSION OF EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 66323(a)(2).
Permit Issued
Issued on 8/18/2025
Issuing Office
Current Status
Issued on 8/18/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/27/2024 APPLICANT
Assigned to Plan Check Engineer 1/3/2025 DANIEL ABRAMYAN
Corrections Issued 1/6/2025 DANIEL ABRAMYAN
Applicant returned to address corrections 1/15/2025 DANIEL ABRAMYAN
Applicant returned to address corrections 4/29/2025 ISIS ARGUETA
Applicant returned to address corrections 5/22/2025 GIOVANNY CHAVEZ
Plan Check Approved 5/28/2025 GIOVANNY CHAVEZ
Issued 8/18/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/6/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/6/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/6/2025 CARLOS AGUILERA
Sewer availability Cleared 1/6/2025 CARLOS AGUILERA
Specific Plan Cleared 4/22/2025 JUDE HERNANDEZ
Grading Pre-Inspection Cleared 5/23/2025 DANIEL ABRAMYAN

Contact Information

Contractor Gad Construction Inc; Lic. No.: 1090519-B       ,
Engineer Khatchadourian,, Vicken; Lic. No.: NA3141       ,

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/30/2025 Partial Inspection BRIAN SULLIVAN
PLUMBING-Rough 10/22/2025 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 10/29/2025 Partial Approval ROY SPAULDING
BUILDING-Rough-Frame 12/22/2025 Not Ready for Inspection ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Partial Approval ROY SPAULDING
Green Building Rough 12/22/2025 Not Ready for Inspection ROY SPAULDING
MERV13>=Rough 12/22/2025 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Rough 1/21/2026 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 1/21/2026 Not Ready for Inspection ROY SPAULDING
Special/Order Compliance 1/21/2026 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 2/24/2026 Corrections Issued ROY SPAULDING
Special/Order Compliance 2/24/2026 Partial Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 3/23/2026 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 4/2/2026 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Rough 4/2/2026 Corrections Issued ROY SPAULDING
Green Building Rough 4/2/2026 Conditional Approval ROY SPAULDING
PLUMBING-Rough 4/2/2026 Approved ROY SPAULDING
BUILDING-Rough-Frame 4/8/2026 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 4/8/2026 Corrections Issued BRIAN SULLIVAN
HVAC-Rough 4/8/2026 Approved BRIAN SULLIVAN
PLUMBING-Rough 4/8/2026 Partial Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 5/1/2026 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 5/1/2026 Approved BRIAN SULLIVAN
Green Building Rough 5/1/2026 Approved BRIAN SULLIVAN
MERV13>=Rough 5/1/2026 Approved BRIAN SULLIVAN
PLUMBING-Rough 5/1/2026 Partial Inspection BRIAN SULLIVAN
Insulation 5/7/2026 Approved ROY SPAULDING
Pre-Inspection 5/7/2026 Partial Inspection BRIAN SULLIVAN
Drywall Nailing 5/26/2026 Approved ROY SPAULDING
Interior/Exterior Lathing 5/26/2026 Approved ROY SPAULDING
Interior/Exterior Lathing 6/2/2026 Approved ROY SPAULDING
Shower Pan 6/2/2026 Approved ROY SPAULDING