131 N CRESCENT HEIGHTS BLVD 90048
Certificate Information: 131 N CRESCENT HEIGHTS BLVD 90048
- Application / Permit
- 24014-10000-05636
- Plan Check / Job No.
- B24LA37268
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF (E) DETACHED GARAGE TO ADU AND OTHER PORTION TO BE STORAGE (ZC: 95 SF). GROUND AND SECOND STORY ADDITION TO ADU PER LAMC 12.22A.33(b)(1)
- Permit Issued
- Issued on 4/22/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2025 | VIVIAN LAO |
| Corrections Issued | 1/16/2025 | VIVIAN LAO |
| Quality Review Completed | 1/22/2025 | KEN GILL |
| Building Plans Picked Up | 1/24/2025 | APPLICANT |
| Plan Check Approved | 4/18/2025 | VIVIAN LAO |
| Issued | 4/22/2025 | APPLICANT |
| CofO in Progress | 2/5/2026 | WILBER ROSALES |
| Permit Finaled | 2/5/2026 | RICHARD STEINBACH |
| CofO Issued | 2/5/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/5/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 1/25/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/25/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/27/2025 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 4/7/2025 | ENRIQUE ACOSTA |
Contact Information
| Contractor | Golden Estate Builders Inc; Lic. No.: 1113809-B | 640 S CURSON AVE APT 305 LOS ANGELES, CA 90036 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/15/2025 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 5/15/2025 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 5/22/2025 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 7/1/2025 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 7/1/2025 | Approved | EVAN COOPER |
| Green Building Rough | 7/1/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 7/1/2025 | Corrections Issued | EVAN COOPER |
| METHANE-Rough | 7/1/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 7/1/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 7/9/2025 | Corrections Issued | ARAM AVEDISIAN |
| Insulation | 7/9/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/11/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 7/11/2025 | Conditional Approval | EVAN COOPER |
| Insulation | 7/11/2025 | Approved | EVAN COOPER |
| Drywall Nailing | 7/23/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 7/23/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 7/24/2025 | Corrections Issued | EVAN COOPER |
| Sewer | 7/24/2025 | Approved | EVAN COOPER |
| Underground Mechanical | 7/24/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 10/21/2025 | No Access for Inspection | EVAN COOPER |
| PLUMBING-Final | 10/21/2025 | No Access for Inspection | EVAN COOPER |
| Smoke Detectors | 10/21/2025 | No Access for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 11/5/2025 | Corrections Issued | EVAN COOPER |
| Final | 11/5/2025 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 11/5/2025 | Approved | EVAN COOPER |
| Green Building Final | 11/5/2025 | Approved | EVAN COOPER |
| HVAC-Final | 11/5/2025 | Corrections Issued | EVAN COOPER |
| METHANE-Barrier | 11/5/2025 | Approved | EVAN COOPER |
| METHANE-Subgrade | 11/5/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 11/5/2025 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 11/5/2025 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 11/5/2025 | Not Ready for Inspection | EVAN COOPER |
| Special/Order Compliance | 11/5/2025 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 11/20/2025 | Not Ready for Inspection | EVAN COOPER |
| Final | 11/20/2025 | Not Ready for Inspection | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 11/20/2025 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 11/20/2025 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 1/30/2026 | Approved | WILBER ROSALES |
| Final | 1/30/2026 | Not Ready for Inspection | WILBER ROSALES |
| HVAC-Final | 1/30/2026 | Approved | WILBER ROSALES |
| PLUMBING-Final | 1/30/2026 | Not Ready for Inspection | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 1/30/2026 | SGSOV Not Ready | WILBER ROSALES |
| Smoke Detectors | 1/30/2026 | Approved | WILBER ROSALES |
| Final | 2/4/2026 | OK to Issue CofO | WILBER ROSALES |
| PLUMBING-Final | 2/4/2026 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 2/4/2026 | SGSOV Approved | WILBER ROSALES |
| Service/Power Release | 2/5/2026 | Approved | WILBER ROSALES |