4235 S ALLA ROAD 90066

Certificate Information: 4235 S ALLA ROAD 90066

Application / Permit
24014-10000-05608
Plan Check / Job No.
B24LA37046
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT WITH ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 1/27/2025
Issuing Office
Current Status
CofO Issued on 7/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2024 APPLICANT
Assigned to Plan Check Engineer 12/24/2024 SERGIO MUNIZ
Corrections Issued 12/25/2024 SERGIO MUNIZ
Applicant returned to address corrections 1/16/2025 SERGIO MUNIZ
Plan Check Approved 1/23/2025 GURUNATH NESARAJAH
Issued 1/27/2025 APPLICANT
CofO in Progress 7/8/2025 MICHAEL ALLEN
Permit Finaled 7/17/2025 RICHARD STEINBACH
CofO Issued 7/17/2025 RICHARD STEINBACH
Permit Finaled 7/17/2025 RICHARD STEINBACH

Permit Application Clearance Information

ZA Case Cleared 12/30/2024 RUBEN VASQUEZ
ZA Case Cleared 12/30/2024 RUBEN VASQUEZ
Address approval Cleared 1/2/2025 KIMBERLY HERNANDEZ
Specific Plan Cleared 1/7/2025 RICHARD WOO
Eng Process Fee Ord 176,300 Cleared 1/14/2025 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 1/14/2025 KIMBERLY HERNANDEZ
Sewer availability Cleared 1/14/2025 KIMBERLY HERNANDEZ

Contact Information

Contractor Build Method Construction Inc; Lic. No.: 1059684-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21731 VENTURA BLVD SUITE 110      WOODLAND HILLS, CA 91364

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/26/2025 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 3/6/2025 Approved MICHAEL ALLEN
Special/Order Compliance 3/6/2025 Partial Approval RUBEN RIVAS
BUILDING-Rough-Frame 3/27/2025 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Rough 3/27/2025 Approved RUBEN RIVAS
Green Building Rough 3/27/2025 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 3/27/2025 Corrections Issued RUBEN RIVAS
PLUMBING-Rough 3/27/2025 Corrections Issued RUBEN RIVAS
Special/Order Compliance 3/27/2025 Partial Inspection TEMISTOCLES CAAL
Interior/Exterior Lathing 4/4/2025 Partial Approval JAYLIN GRAVITTE
HVAC-Rough 4/7/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 4/7/2025 Approved MICHAEL ALLEN
Special/Order Compliance 4/7/2025 Corrections Issued MICHAEL ALLEN
BUILDING-Rough-Frame 4/10/2025 Approved BOBBY KEY
Drywall Nailing 4/10/2025 Corrections Issued BOBBY KEY
Green Building Rough 4/10/2025 Approved BOBBY KEY
Insulation 4/10/2025 Approved BOBBY KEY
Drywall Nailing 4/15/2025 Conditional Approval JAYLIN GRAVITTE
Gas Test 5/12/2025 Corrections Issued JAYLIN GRAVITTE
Sewer 5/12/2025 Approved JAYLIN GRAVITTE
Underground Mechanical 5/12/2025 Partial Approval JAYLIN GRAVITTE
Shower Pan 5/16/2025 Approved JAYLIN GRAVITTE
Special/Order Compliance 5/16/2025 Partial Inspection HERBERT GIRON
Special/Order Compliance 5/16/2025 Partial Inspection TEMISTOCLES CAAL
Gas Test 5/27/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 5/27/2025 Approved JAYLIN GRAVITTE
ELECTRICAL-Final 6/30/2025 Partial Approval MICHAEL ALLEN
Final 6/30/2025 Corrections Issued MICHAEL ALLEN
Green Building Final 6/30/2025 Approved MICHAEL ALLEN
HVAC-Final 6/30/2025 Partial Approval MICHAEL ALLEN
PLUMBING-Final 6/30/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 6/30/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 6/30/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 7/3/2025 Approved MICHAEL ALLEN
Final 7/3/2025 Corrections Issued MICHAEL ALLEN
HVAC-Final 7/3/2025 Approved MICHAEL ALLEN
PLUMBING-Final 7/3/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 7/8/2025 Approved MICHAEL ALLEN
Final 7/8/2025 OK to Issue CofO MICHAEL ALLEN
HVAC-Final 7/8/2025 Approved MICHAEL ALLEN
PLUMBING-Final 7/8/2025 Approved MICHAEL ALLEN