13467 W RELIANCE ST 91331
Certificate Information: 13467 W RELIANCE ST 91331
- Application / Permit
- 24014-10000-05606
- Plan Check / Job No.
- B24LA37034
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AT SIDE OF EXISTING 1-STORY SFD ATTACHED TO THE KITCHEN PER ENGINEER
- Permit Issued
- Issued on 3/12/2025
- Issuing Office
- Current Status
- CofO Issued on 9/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2024 | JOSEPH RAFOLS |
| Corrections Issued | 12/24/2024 | JOSEPH RAFOLS |
| Building Plans Picked Up | 1/2/2025 | APPLICANT |
| Plan Check Approved | 3/12/2025 | ALEC MOUSAKHANIAN |
| Issued | 3/12/2025 | APPLICANT |
| CofO in Progress | 8/22/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
| CofO Issued | 9/4/2025 | RUBEN SALAS |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 3/11/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/11/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Ec Renewables Inc; Lic. No.: 1132619-B | 5345 WHITE OAK AVE UNIT G ENCINO, CA 91316 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/1/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/1/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/7/2025 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 4/7/2025 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/11/2025 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 4/11/2025 | Not Ready for Inspection | WILLIAM WREN |
| Deputy Wood Construction | 4/14/2025 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/21/2025 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/1/2025 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/1/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/1/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/1/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/7/2025 | Approved | VINCENT HANLEY |
| Drywall Nailing | 5/7/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 8/21/2025 | Approved | JENNIFER RABUCHIN |
| Final | 8/21/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 8/21/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/21/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/21/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/21/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 8/21/2025 | Approved | JENNIFER RABUCHIN |