13467 W RELIANCE ST 91331

Certificate Information: 13467 W RELIANCE ST 91331

Application / Permit
24014-10000-05606
Plan Check / Job No.
B24LA37034
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AT SIDE OF EXISTING 1-STORY SFD ATTACHED TO THE KITCHEN PER ENGINEER
Permit Issued
Issued on 3/12/2025
Issuing Office
Current Status
CofO Issued on 9/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2024 APPLICANT
Assigned to Plan Check Engineer 12/23/2024 JOSEPH RAFOLS
Corrections Issued 12/24/2024 JOSEPH RAFOLS
Building Plans Picked Up 1/2/2025 APPLICANT
Plan Check Approved 3/12/2025 ALEC MOUSAKHANIAN
Issued 3/12/2025 APPLICANT
CofO in Progress 8/22/2025 JENNIFER RABUCHIN
Permit Finaled 9/4/2025 RUBEN SALAS
CofO Issued 9/4/2025 RUBEN SALAS
Permit Finaled 9/4/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/11/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 3/11/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/11/2025 LEE GUILBEAUX

Contact Information

Contractor Ec Renewables Inc; Lic. No.: 1132619-B 5345 WHITE OAK AVE   UNIT G    ENCINO, CA 91316
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/1/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 4/1/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/7/2025 Partial Approval VINCENT HANLEY
Green Building Rough 4/7/2025 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 4/11/2025 Corrections Issued WILLIAM WREN
Green Building Rough 4/11/2025 Not Ready for Inspection WILLIAM WREN
Deputy Wood Construction 4/14/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Approved VINCENT HANLEY
Green Building Rough 4/21/2025 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 5/1/2025 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 5/1/2025 Approved VINCENT HANLEY
Green Building Rough 5/1/2025 Approved VINCENT HANLEY
PLUMBING-Rough 5/1/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/7/2025 Approved VINCENT HANLEY
Drywall Nailing 5/7/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 8/21/2025 Approved JENNIFER RABUCHIN
Final 8/21/2025 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 8/21/2025 Approved JENNIFER RABUCHIN
HVAC-Final 8/21/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/21/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/21/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 8/21/2025 Approved JENNIFER RABUCHIN