5944 W 74TH ST 90045

Certificate Information: 5944 W 74TH ST 90045

Application / Permit
24014-10000-05569
Plan Check / Job No.
B24LA36714
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: 2-story addition to an existing 1-story single family dwelling + attached JADU. Major remodel - only West wall to remain. Sprinklers required per NFPA 13D.
Permit Issued
Issued on 4/18/2025
Issuing Office
Current Status
Issued on 4/18/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/20/2024 APPLICANT
Assigned to Plan Check Engineer 12/26/2024 PRANITA SHAH
Corrections Issued 1/16/2025 PRANITA SHAH
Quality Review Completed 1/31/2025 HERNAN ARREOLA
Applicant returned to address corrections 2/4/2025 PRANITA SHAH
Applicant returned to address corrections 3/4/2025 PRANITA SHAH
Plan Check Approved 4/18/2025 PRANITA SHAH
Issued 4/18/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/17/2025 DARIN LAM
Sewer availability Cleared 3/17/2025 DARIN LAM
GPI Written Notices Cleared 3/19/2025 PRANITA SHAH
Grading Pre-Inspection Cleared 3/19/2025 PRANITA SHAH
Roof/Waste drainage to street Cleared 3/24/2025 WALLIE JONG
Specific Plan Cleared 3/24/2025 HAMID GHAEMMAGHAMI
Miscellaneous Cleared 3/25/2025 DIANA RENTERIA

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/15/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/19/2025 Partial Approval JESUS PINEDA
PLUMBING-Rough 5/19/2025 Partial Approval JESUS PINEDA
Insulation 5/20/2025 Approved RUBEN RIVAS
Deputy Wood Construction 5/21/2025 Conditional Approval JAYLIN GRAVITTE
Floor/Roof Diaphrgm/Shear Wall 5/21/2025 Partial Approval JAYLIN GRAVITTE
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 6/24/2025 Corrections Issued RUBEN RIVAS
ELECTRICAL-Rough 6/24/2025 Corrections Issued RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 6/24/2025 Not Ready for Inspection RUBEN RIVAS
Green Building Rough 6/24/2025 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 6/24/2025 Not Ready for Inspection RUBEN RIVAS
MERV13>=Rough 6/24/2025 Not Ready for Inspection RUBEN RIVAS
PLUMBING-Rough 6/24/2025 Approved RUBEN RIVAS
Rough-Elec/Plmb/HVAC 6/26/2025 Approved RUBEN RIVAS
Wood Frame 6/26/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 7/8/2025 Corrections Issued RUBEN RIVAS
Interior/Exterior Lathing 7/11/2025 Partial Approval JAYLIN GRAVITTE
BUILDING-Rough-Frame 7/15/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 7/15/2025 Approved ANTHONY EGSON
Insulation 7/15/2025 Approved ANTHONY EGSON
Drywall Nailing 7/21/2025 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Rough 7/21/2025 Partial Approval RUBEN RIVAS
Interior/Exterior Lathing 7/21/2025 Not Ready for Inspection RUBEN RIVAS
Shower Pan 7/21/2025 Approved RUBEN RIVAS
Underground Mechanical 7/21/2025 Corrections Issued RUBEN RIVAS
Drywall Nailing 8/8/2025 Approved RUBEN RIVAS
Underground Mechanical 8/8/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 9/25/2025 Approved JESUS PINEDA
ELECTRICAL-Final 9/25/2025 Corrections Issued JESUS PINEDA
MERV13>=Rough 9/25/2025 Approved JESUS PINEDA
Smoke Detectors 9/25/2025 Corrections Issued JESUS PINEDA
Verify Sprinkler Sign Off 9/25/2025 Approved JESUS PINEDA
ELECTRICAL-Final 10/2/2025 Approved JESUS PINEDA
Final 10/2/2025 Corrections Issued JESUS PINEDA
Gas Test 10/2/2025 Corrections Issued JESUS PINEDA
Green Building Final 10/2/2025 Corrections Issued JESUS PINEDA
HVAC-Final 10/2/2025 Approved JESUS PINEDA
MERV13>=Final 10/2/2025 Approved JESUS PINEDA
PLUMBING-Final 10/2/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 10/2/2025 SGSOV Approved JESUS PINEDA
Smoke Detectors 10/2/2025 Approved JESUS PINEDA
Gas Test 10/10/2025 Approved HERBERT GIRON
Service/Power Release 10/10/2025 Approved HERBERT GIRON