1912 S WALGROVE AVE 90066
Certificate Information: 1912 S WALGROVE AVE 90066
- Application / Permit
- 24014-10000-05564
- Plan Check / Job No.
- B24LA36636
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND 2ND STORY ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING NFPA 13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 6/9/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2025 | JAD BASMA |
| Corrections Issued | 1/5/2025 | JAD BASMA |
| Quality Review Completed | 1/14/2025 | KEN GILL |
| Building Plans Picked Up | 1/15/2025 | APPLICANT |
| Plan Check Approved | 3/24/2025 | JAD BASMA |
| Issued | 6/9/2025 | APPLICANT |
| CofO in Progress | 5/12/2026 | DAKOTA LOW |
| Permit Finaled | 5/15/2026 | RICHARD STEINBACH |
| CofO Issued | 5/15/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/15/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 1/15/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2025 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 1/29/2025 | DARIN LAM |
| Hydrant and Access approval | Cleared | 3/13/2025 | JERRY KAO |
| Specific Plan | Cleared | 3/13/2025 | RICHARD WOO |
| Grading Pre-Inspection | Cleared | 3/24/2025 | JAD BASMA |
Contact Information
| Contractor | Waconah Construction; Lic. No.: 908219-B | 218 STEPNEY STREET INGLEWOOD, CA 90302 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/10/2025 | Corrections Issued | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 6/16/2025 | Partial Approval | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 6/23/2025 | Partial Approval | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 6/27/2025 | Approved | MICHAEL ALLEN |
| Sewer | 7/1/2025 | Approved | JAYLIN GRAVITTE |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Partial Approval | MICHAEL ALLEN |
| Underground Mechanical | 7/16/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Underground Mechanical | 7/21/2025 | Approved | WILBER ROSALES |
| HVAC-Rough | 8/8/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Rough | 8/15/2025 | Approved | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Corrections Issued | WILBER ROSALES |
| BUILDING-Rough-Frame | 9/4/2025 | Corrections Issued | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Approved | WILBER ROSALES |
| Green Building Rough | 9/4/2025 | Not Ready for Inspection | WILBER ROSALES |
| PLUMBING-Rough | 9/4/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 9/22/2025 | Approved | WILBER ROSALES |
| Green Building Rough | 9/22/2025 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 9/22/2025 | Partial Approval | WILBER ROSALES |
| Insulation | 10/1/2025 | Approved | WILBER ROSALES |
| Drywall Nailing | 10/7/2025 | Approved | WILBER ROSALES |
| Shower Pan | 10/10/2025 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 10/14/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 1/29/2026 | Partial Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 2/11/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Final | 2/17/2026 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 3/9/2026 | Corrections Issued | DAKOTA LOW |
| Underground Mechanical | 3/9/2026 | Partial Approval | DAKOTA LOW |
| HVAC-Final | 3/13/2026 | Corrections Issued | DAKOTA LOW |
| ELECTRICAL-Final | 3/26/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 3/26/2026 | Approved | ANTHONY EGSON |
| HVAC-Final | 4/17/2026 | Approved | DAKOTA LOW |
| Final | 4/20/2026 | Corrections Issued | DAKOTA LOW |
| Final | 5/11/2026 | OK to Issue CofO | DAKOTA LOW |
| Footing/Foundation/Slab | 5/11/2026 | Approved | DAKOTA LOW |
| Green Building Final | 5/11/2026 | Approved | DAKOTA LOW |
| SGSOV-Seismic Gas S/O Valve | 5/11/2026 | SGSOV Approved | DAKOTA LOW |
| Smoke Detectors | 5/11/2026 | Approved | DAKOTA LOW |
| Service/Power Release | 5/12/2026 | Approved | DAKOTA LOW |