1101 S LA BREA AVE 90019
Certificate Information: 1101 S LA BREA AVE 90019
- Application / Permit
- 24014-10000-05555
- Plan Check / Job No.
- B24LA36570
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (17) Coffee Shop
- Work Description
- Change of use from retail to Coffee Shop and Add Mezzanine Storage
- Permit Issued
- Issued on 11/3/2025
- Issuing Office
- Metro
- Current Status
- Issued on 11/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2024 | HERNAN ARREOLA |
| Assigned to Zoning Architect | 12/19/2024 | JASON BRAVO |
| Corrections Issued | 12/27/2024 | HERNAN ARREOLA |
| Quality Review Completed | 12/27/2024 | PETER KIM |
| Building Plans Picked Up | 12/30/2024 | APPLICANT |
| Disabled Access Plans Picked Up | 12/30/2024 | APPLICANT |
| Green Plans Picked Up | 12/30/2024 | APPLICANT |
| Plan Check Approved | 8/25/2025 | HERNAN ARREOLA |
| Issued | 11/3/2025 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 4/30/2025 | CLAUDE GOODING |
| Miscellaneous | Cleared | 4/30/2025 | CLAUDE GOODING |
| DAS Clearance | Cleared | 6/10/2025 | SHINE LIN |
| Zoning Plan Check | Cleared | 7/8/2025 | JASON BRAVO |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 8/6/2025 | DAVID LOPEZ |
Contact Information
| Contractor | Builtech Group Inc; Lic. No.: 982574-B | 6007 BUCKLER AVENUE LOS ANGELES, CA 90043 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/3/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| METHANE-Barrier | 2/3/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| METHANE-Subgrade | 2/3/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Footing/Foundation/Slab | 3/6/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| METHANE-Barrier | 3/6/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| METHANE-Subgrade | 3/6/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |