3802 S CLOVERDALE AVE 90008
Certificate Information: 3802 S CLOVERDALE AVE 90008
- Application / Permit
- 24014-10000-05538
- Plan Check / Job No.
- B24LA36400
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN REMODEL AND SECOND STORY ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLIN WITH ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 3/12/2025
- Issuing Office
- Current Status
- Issued on 3/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2025 | JAD BASMA |
| Corrections Issued | 1/5/2025 | JAD BASMA |
| Quality Review Completed | 1/6/2025 | GARO TELMI |
| Applicant returned to address corrections | 3/6/2025 | JAD BASMA |
| Plan Check Approved | 3/12/2025 | JAD BASMA |
| Issued | 3/12/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/3/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2025 | WALLIE JONG |
| Sewer availability | Cleared | 2/4/2025 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 2/25/2025 | RUEL COLE |
| Grading Pre-Inspection | Cleared | 3/6/2025 | JAD BASMA |
Contact Information
| Architect | Grist,, John Kenneth; Lic. No.: NA4295 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/15/2025 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 5/1/2025 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 5/1/2025 | Approved | LUIS CASTRO |
| Deputy Drilled-In Anchors | 5/2/2025 | Partial Approval | LUIS CASTRO |
| Deputy Steel/Welding | 5/13/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2025 | Conditional Approval | LUIS CASTRO |
| Sewer | 6/25/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 7/1/2025 | Conditional Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 7/1/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 7/1/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 7/9/2025 | Partial Approval | LUIS CASTRO |
| Insulation | 7/14/2025 | Approved | RONNIE MEDINA |
| Drywall Nailing | 7/17/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 7/17/2025 | Approved | RONNIE MEDINA |
| Shower Pan | 7/17/2025 | Approved | RONNIE MEDINA |
| BUILDING-Rough-Frame | 9/24/2025 | Approved | BRENDAN MORELLI |
| Final | 9/24/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 9/24/2025 | Approved | BRENDAN MORELLI |
| Green Building Rough | 9/24/2025 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 9/24/2025 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 9/24/2025 | Approved | BRENDAN MORELLI |
| Sewer | 9/29/2025 | Not Ready for Inspection | LUIS CASTRO |
| Sewer | 9/30/2025 | Not Ready for Inspection | LUIS CASTRO |
| Final | 10/1/2025 | Partial Approval | LUIS CASTRO |