7854 S TRUXTON AVE 90045
Certificate Information: 7854 S TRUXTON AVE 90045
- Application / Permit
- 24014-10000-05518
- Plan Check / Job No.
- B24LA36282
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan Addition and major remodel of existing single family residence. Fire Sprinkler
- Permit Issued
- Issued on 4/17/2025
- Issuing Office
- Current Status
- CofO Issued on 2/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2025 | KHEDER ALRAZAA |
| Corrections Issued | 1/13/2025 | KHEDER ALRAZAA |
| Quality Review Completed | 1/14/2025 | GARO TELMI |
| Applicant returned to address corrections | 3/18/2025 | KHEDER ALRAZAA |
| Plan Check Approved | 4/15/2025 | KHEDER ALRAZAA |
| Issued | 4/17/2025 | APPLICANT |
| CofO in Progress | 2/13/2026 | JESUS PINEDA |
| Permit Finaled | 2/17/2026 | RICHARD STEINBACH |
| CofO Issued | 2/17/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/17/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2025 | DARIN LAM |
| Sewer availability | Cleared | 1/14/2025 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 2/13/2025 | VASIL MIHALEV |
| Construction near power lines | Cleared | 3/5/2025 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 3/29/2025 | DARIN LAM |
| GPI Written Notices | Cleared | 4/15/2025 | KHEDER ALRAZAA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/5/2025 | Approved | JESUS PINEDA |
| Special/Order Compliance | 5/5/2025 | Corrections Issued | JESUS PINEDA |
| Special/Order Compliance | 5/5/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2025 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 5/29/2025 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2025 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 8/29/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 8/29/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 9/9/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 9/9/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2025 | Approved | JESUS PINEDA |
| Green Building Rough | 9/9/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 9/9/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 9/9/2025 | Partial Approval | JESUS PINEDA |
| Verify Sprinkler Sign Off | 9/9/2025 | Approved | JESUS PINEDA |
| Insulation | 9/29/2025 | Corrections Issued | JESUS PINEDA |
| Shower Pan | 9/29/2025 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 10/3/2025 | Approved | JESUS PINEDA |
| Insulation | 10/3/2025 | Approved | JESUS PINEDA |
| Shower Pan | 10/3/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 10/7/2025 | Approved | JAYLIN GRAVITTE |
| ELECTRICAL-Final | 2/2/2026 | Corrections Issued | JESUS PINEDA |
| Final | 2/2/2026 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 2/2/2026 | Approved | JESUS PINEDA |
| HVAC-Final | 2/2/2026 | Approved | JESUS PINEDA |
| PLUMBING-Final | 2/2/2026 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 2/2/2026 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 2/2/2026 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 2/13/2026 | Approved | JESUS PINEDA |
| Final | 2/13/2026 | OK to Issue CofO | JESUS PINEDA |
| Service/Power Release | 2/13/2026 | Approved | JESUS PINEDA |