1478 W MORTON PL 90026

Certificate Information: 1478 W MORTON PL 90026

Application / Permit
24014-10000-05515
Plan Check / Job No.
B24LA36247
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 288 SQ. FT. AND A NEW DECK OF 81 SQ. FT. PER ENGINEER OF RECORD.
Permit Issued
Issued on 3/10/2025
Issuing Office
Valley
Current Status
CofO Issued on 4/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2024 APPLICANT
Assigned to Plan Check Engineer 12/20/2024 SAMUEL GONZALEZ
Corrections Issued 12/21/2024 SAMUEL GONZALEZ
Building Plans Picked Up 1/6/2025 APPLICANT
Applicant returned to address corrections 1/24/2025 ZAW HAN
Applicant returned to address corrections 2/11/2025 CRISTINA SALAZAR
Plan Check Approved 2/21/2025 JOHN MESIAS
Issued 3/10/2025 APPLICANT
CofO in Progress 4/6/2026 HAMIK HARTOUNIAN
Permit Finaled 4/7/2026 DEROLD HAUFF
CofO Issued 4/7/2026 DEROLD HAUFF
Permit Finaled 4/7/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/18/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/21/2025 CARLOS AGUILERA
Grading Pre-Inspection Cleared 1/21/2025 LANNY MERRICK
Tenant Habitability Plan Cleared 1/23/2025 KORNEL LELEA

Contact Information

Contractor I B A Builders Inc; Lic. No.: 1074505-B 145 S FAIRFAX AVE STE 200      LOS ANGELES, CA 90036

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/21/2025 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/21/2025 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/26/2025 Approved HAMIK HARTOUNIAN
Underground Mechanical 4/3/2025 Approved WILLIAM SIERRA
Insulation 4/7/2025 Partial Approval JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 4/9/2025 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 5/15/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 5/15/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 5/30/2025 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 6/2/2025 Approved ARTHUR NEGRETE
Green Building Rough 6/2/2025 Approved ARTHUR NEGRETE
HVAC-Rough 6/2/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 6/2/2025 Approved ARTHUR NEGRETE
Insulation 6/3/2025 Not Ready for Inspection ALEX COLIN
Insulation 6/5/2025 Corrections Issued JOSH MEISTER
Insulation 6/9/2025 Approved ANTHONY RAMOS
Drywall Nailing 6/16/2025 Approved ANTHONY RAMOS
Shower Pan 6/26/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/30/2025 Approved ALEX COLIN
Special/Order Compliance 6/30/2025 Approved ALEX COLIN
Special/Order Compliance 6/30/2025 Partial Inspection DEVON JACKSON
ELECTRICAL-Final 8/5/2025 Corrections Issued HAMIK HARTOUNIAN
Final 8/5/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 8/5/2025 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 8/5/2025 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/5/2025 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 8/5/2025 Corrections Issued HAMIK HARTOUNIAN
Special/Order Compliance 8/5/2025 Partial Inspection OSVALDO PARAMO
Final 1/30/2026 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 1/30/2026 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/30/2026 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 1/30/2026 Approved HAMIK HARTOUNIAN
Final 4/2/2026 OK to Issue CofO HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/2/2026 SGSOV Approved HAMIK HARTOUNIAN