4560-4560 1/2 W 18TH ST 90019
Certificate Information: 4560-4560 1/2 W 18TH ST 90019
- Application / Permit
- 24014-10000-05503
- Plan Check / Job No.
- B24LA36152
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- [ePlan] 2ND FLOOR ADDITION TO (E) 1-STORY SFD TO HAVE ATTACHED ADU PER LAMC 12.22 A.33 (c) & (e) OVER (N) PATIO COVER
- Permit Issued
- Issued on 3/20/2025
- Issuing Office
- Current Status
- CofO Issued on 1/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 12/22/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 12/24/2024 | TU HUA |
| Applicant returned to address corrections | 2/26/2025 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 3/20/2025 | MAHNAZ NOURHASHEMI |
| Issued | 3/20/2025 | APPLICANT |
| CofO in Progress | 1/30/2026 | OSVALDO PARAMO |
| Permit Finaled | 1/30/2026 | DEROLD HAUFF |
| Permit Finaled | 1/30/2026 | DEROLD HAUFF |
| CofO Issued | 1/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/11/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/25/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Zetino And Son'S Construction; Lic. No.: 817787-B | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/24/2025 | Corrections Issued | ENRIQUE MIRELES |
| METHANE-Barrier | 4/24/2025 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 4/24/2025 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 5/1/2025 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/1/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2025 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Corrections Issued | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Partial Approval | JUSTIN HAWLEY |
| Sewer | 7/22/2025 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 7/30/2025 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/5/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 8/5/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Rough | 8/5/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 8/5/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 9/4/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Green Building Rough | 9/4/2025 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 9/4/2025 | Corrections Issued | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/4/2025 | Partial Approval | JUSTIN HAWLEY |
| Shower Pan | 9/4/2025 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 9/11/2025 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 9/11/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 9/15/2025 | Corrections Issued | ALEX COLIN |
| Drywall Nailing | 9/25/2025 | Approved | ALEX COLIN |
| Insulation | 9/25/2025 | Approved | ALEX COLIN |
| SGSOV-Seismic Gas S/O Valve | 11/25/2025 | SGSOV Not Ready | JUSTIN HAWLEY |
| Final | 12/2/2025 | Corrections Issued | JUSTIN HAWLEY |
| Smoke Detectors | 12/2/2025 | Approved | JUSTIN HAWLEY |
| Final | 1/28/2026 | OK to Issue CofO | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Approved | OSVALDO PARAMO |