4252 N BRUNSWICK AVE 90039

Certificate Information: 4252 N BRUNSWICK AVE 90039

Application / Permit
24014-10000-05466
Plan Check / Job No.
B24LA35870
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GARAGE CONVERSION AND ADDITION TO A DETACHED 1-STORY ADU PER ENGINEER DETAILS (Ordinance ADU Type, New Construction , or Conversion of Existing, LAMC 12.22 A.33(b)(1))
Permit Issued
Issued on 7/31/2025
Issuing Office
Metro
Current Status
Issued on 7/31/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/12/2024 APPLICANT
Assigned to Plan Check Engineer 12/13/2024 LUKE GONZALES
Corrections Issued 12/14/2024 LUKE GONZALES
Building Plans Picked Up 12/19/2024 APPLICANT
Plan Check Approved 2/14/2025 AUNG SOE
Issued 7/31/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 12/19/2024 THERESA NGUYEN
Address approval Cleared 1/7/2025 AMBER CAMPBELL
ZI Cleared 1/9/2025 JASON CHAN
Eng Process Fee Ord 176,300 Cleared 1/10/2025 AMBER CAMPBELL
Sewer availability Cleared 1/10/2025 AMBER CAMPBELL
Roof/Waste drainage to street Cleared 2/12/2025 AMBER CAMPBELL

Contact Information

Architect Bo, Kyle Sundius; Lic. No.: C38566 1814 BROOKS AVE      LOS ANGELES, CA 90012
Contractor Jung Christopher; Lic. No.: 704277-B 813 N SIERRA BONITA AVE      LOS ANGELES, CA 90046
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/5/2025 Partial Inspection NICHOLAS LOPEZ
PLUMBING-Rough 9/3/2025 Partial Approval NICHOLAS LOPEZ
Excavation/Setback/Form/Re-Bar 9/23/2025 Partial Approval NICHOLAS LOPEZ
Special/Order Compliance 9/23/2025 Corrections Issued NICHOLAS LOPEZ
Deputy Drilled-In Anchors 10/3/2025 Approved NICHOLAS LOPEZ
Excavation/Setback/Form/Re-Bar 10/3/2025 Approved NICHOLAS LOPEZ
Deputy Wood Construction 11/19/2025 Conditional Approval NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 11/19/2025 Conditional Approval NICHOLAS LOPEZ
Insulation 12/12/2025 Partial Approval NICHOLAS LOPEZ
Rough-Elec/Plmb/HVAC 12/12/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 1/27/2026 Partial Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 2/4/2026 Approved NICHOLAS LOPEZ
Green Building Rough 2/4/2026 Approved NICHOLAS LOPEZ
Insulation 2/19/2026 Approved DAVID WILLIAMS
Interior/Exterior Lathing 2/19/2026 Partial Approval DAVID WILLIAMS
Shower Pan 2/19/2026 Approved DAVID WILLIAMS
Smoke Detectors 2/19/2026 Approved DAVID WILLIAMS
Structural Steel Frame 2/19/2026 Approved DAVID WILLIAMS
Drywall Nailing 3/11/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 4/9/2026 Approved NICHOLAS LOPEZ